20445 W LANARK ST 91306

Certificate Information: 20445 W LANARK ST 91306

Application / Permit
20014-20000-01186
Plan Check / Job No.
B20VN04485
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
42'-8" X 20'-2" ADDITION TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 5/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 ALDOUS CHIC
Corrections Issued 3/13/2020 ALDOUS CHIC
Applicant returned to address corrections 5/13/2020 ROSENDO MEDINA
Plan Check Approved 5/18/2020 ROSENDO MEDINA
Issued 5/18/2020 LADBS
CofO in Progress 9/23/2020 HENRY KIM
Permit Finaled 9/24/2020 JOHN JANSON
CofO Issued 9/24/2020 JOHN JANSON
Permit Finaled 9/24/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 5/8/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/11/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C91162 122 N GRAMERCY PL      L.A., CA 90004

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/16/2020 Partial Approval HENRY KIM
Footing/Foundation/Slab 6/18/2020 Approved HENRY KIM
Pre-Inspection 6/26/2020 Approved HENRY KIM
Underground Mechanical 6/26/2020 Approved HENRY KIM
ELECTRICAL-Rough 7/7/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval HENRY KIM
HVAC-Rough 7/7/2020 Approved HENRY KIM
PLUMBING-Rough 7/7/2020 Approved HENRY KIM
BUILDING-Rough-Frame 7/9/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/9/2020 Approved HENRY KIM
Green Building Rough 7/9/2020 Approved HENRY KIM
Drywall Nailing 7/13/2020 Approved HENRY KIM
Insulation 7/13/2020 Approved HENRY KIM
Interior/Exterior Lathing 7/13/2020 Approved HENRY KIM
Interior/Exterior Lathing 7/13/2020 Partial Approval HENRY KIM
Shower Pan 7/13/2020 Approved HENRY KIM
ELECTRICAL-Final 9/10/2020 Corrections Issued HENRY KIM
Final 9/10/2020 Corrections Issued HENRY KIM
Gas Test 9/10/2020 Approved HENRY KIM
Green Building Final 9/10/2020 Approved HENRY KIM
HVAC-Final 9/10/2020 Corrections Issued HENRY KIM
PLUMBING-Final 9/10/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Not Ready HENRY KIM
Smoke Detectors 9/10/2020 Approved HENRY KIM
Final 9/17/2020 Not Ready for Inspection HENRY KIM
HVAC-Final 9/17/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Approved HENRY KIM
ELECTRICAL-Final 9/23/2020 Approved HENRY KIM
Final 9/23/2020 OK to Issue CofO HENRY KIM
PLUMBING-Final 9/23/2020 Approved HENRY KIM