17456 W SATICOY ST 91406

Certificate Information: 17456 W SATICOY ST 91406

Application / Permit
20014-20000-01185
Plan Check / Job No.
B20VN04483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 14' X 20' (E) GARAGE AND ADD 13' X 13'-6" INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 3/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 RAPHAEL ROSAS
Issued 3/13/2020 LADBS
CofO in Progress 5/14/2024 RAUL OLAGI
CofO in Progress 11/18/2024 RAUL OLAGI
CofO in Progress 11/19/2024 RAUL OLAGI
Permit Finaled 11/22/2024 RUBEN SALAS
CofO Issued 11/22/2024 RUBEN SALAS
Permit Finaled 11/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/13/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/13/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/13/2020 LEE GUILBEAUX
Sewer availability Cleared 3/13/2020 LEE GUILBEAUX

Contact Information

No Data Available.

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/12/2020 Corrections Issued GREGG CUMMINGS
Deputy Drilled-In Anchors 6/30/2020 Conditional Approval BEAU COLLINS
Footing/Foundation/Slab 7/8/2020 Approved DANIEL DREW
Underground Mechanical 7/8/2020 Corrections Issued DANIEL DREW
Excavation/Setback/Form/Re-Bar 7/10/2020 Approved DANIEL DREW
Underground Mechanical 7/10/2020 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 9/15/2020 No Access for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 No Access for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Inspection WILLIAM KUEHN
Interior/Exterior Lathing 9/29/2020 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 11/30/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 11/30/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 11/30/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 12/22/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 12/22/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 12/22/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 12/22/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 1/5/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 1/5/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 1/5/2021 Approved ARTHUR SARGSYAN
Insulation 1/22/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 6/2/2021 Approved ALIZAH MAYAGOITIA
Shower Pan 11/7/2023 Approved RAUL OLAGI
ELECTRICAL-Final 3/21/2024 No Access for Inspection RAUL OLAGI
Service/Power Release 3/21/2024 No Access for Inspection RAUL OLAGI
Pre-Inspection 3/26/2024 No Access for Inspection RAUL OLAGI
BUILDING-Rough-Frame 4/10/2024 Approved RAUL OLAGI
Final 4/10/2024 Corrections Issued RAUL OLAGI
Green Building Final 4/10/2024 Approved RAUL OLAGI
Green Building Rough 4/10/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/10/2024 Corrections Issued RAUL OLAGI
Final 4/26/2024 Corrections Issued SALVADOR MARTINEZ
Smoke Detectors 4/26/2024 Corrections Issued SALVADOR MARTINEZ
Final 5/10/2024 Corrections Issued RAUL OLAGI
Smoke Detectors 5/10/2024 Approved RAUL OLAGI
Final 5/13/2024 OK to Issue CofO RAUL OLAGI
Service/Power Release 5/13/2024 Approved RAUL OLAGI