10500 N MELVIN AVE 91326
Certificate Information: 10500 N MELVIN AVE 91326
- Application / Permit
- 20014-20000-01179
- Plan Check / Job No.
- B20VN04470
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 13' X 38' -2" PATIO COVER TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL TO TWO BATHROOM. WINDOWS CHANGE OUTSAME SIZE AND TYPE. KITCHEN REMODEL. RAISING HALL WAY CEILING HEIGHT. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 3/20/2020
- Issuing Office
- Valley
- Current Status
- Issued on 3/20/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SELLA BENYAMIN |
| Corrections Issued | 3/19/2020 | SELLA BENYAMIN |
| Plan Check Approved | 3/20/2020 | PINANK PATEL |
| Issued | 3/20/2020 | LADBS |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 3/19/2020 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 3/20/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 5/14/2020 | Partial Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 6/22/2020 | Partial Approval | HAGOP BADOSSIAN |
| HVAC-Rough | 6/22/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 6/22/2020 | Partial Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 8/11/2020 | Approved | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 8/11/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 8/11/2020 | Approved | HAGOP BADOSSIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Interior/Exterior Lathing | 8/27/2020 | Partial Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 9/4/2020 | Corrections Issued | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 9/4/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 9/4/2020 | Approved | HAGOP BADOSSIAN |
| Wood Frame | 10/2/2020 | Approved | HAGOP BADOSSIAN |
| Interior/Exterior Lathing | 7/28/2022 | Partial Approval | JOHN STEPHENS |
| Interior/Exterior Lathing | 8/1/2022 | Approved | JOHN STEPHENS |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | ARIS ALLAHVERDIAN |
| ELECTRICAL-Final | 4/5/2023 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Final | 4/5/2023 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Footing/Foundation/Slab | 4/5/2023 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| HVAC-Final | 4/5/2023 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| PLUMBING-Final | 4/5/2023 | Corrections Issued | ARIS ALLAHVERDIAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Not Ready | ARIS ALLAHVERDIAN |
| Smoke Detectors | 4/5/2023 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| ELECTRICAL-Final | 7/3/2024 | Not Ready for Inspection | ARA SINANIAN |
| Final | 7/3/2024 | Not Ready for Inspection | ARA SINANIAN |
| Footing/Foundation/Slab | 7/3/2024 | Not Ready for Inspection | ARA SINANIAN |
| HVAC-Final | 7/3/2024 | Not Ready for Inspection | ARA SINANIAN |
| PLUMBING-Final | 7/3/2024 | Not Ready for Inspection | ARA SINANIAN |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | ARA SINANIAN |
| Smoke Detectors | 7/3/2024 | Approved | ARA SINANIAN |