11262 W BLIX ST 91602
Certificate Information: 11262 W BLIX ST 91602
- Application / Permit
- 20014-20000-01178
- Plan Check / Job No.
- B20VN04458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO DETACHED ADU WITH ADDITION OF 34'X 20' PER ORDINANCE
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 5/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | CRYSTEL MAALOUF |
| Green Plans Picked Up | 4/9/2020 | APPLICANT |
| Corrections Issued | 4/17/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/22/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 4/23/2020 | APPLICANT |
| Applicant returned to address corrections | 8/19/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/28/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/8/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/24/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/2/2020 | CRYSTEL MAALOUF |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 4/28/2022 | DAVID MATSON |
| Permit Finaled | 5/11/2022 | MICHAEL SMITH |
| CofO Issued | 5/11/2022 | MICHAEL SMITH |
| Permit Finaled | 5/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 4/16/2020 | DAVID MATSON |
| Address approval | Cleared | 4/27/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/27/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2020 | ROSE MARIE SMITH |
| Construction near power lines | Cleared | 6/10/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/20/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/29/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Yourico Construction Inc; Lic. No.: 594159-B | 1241 N THOMPSON AVENUE GLENDALE, CA 91201 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 13719 OXNARD ST 101 VAN NUYS, CA 91401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2020 | Partial Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 11/2/2020 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Corrections Issued | THOMAS FINNILA |
| Reinforced Concrete Frame | 11/9/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 11/12/2020 | Conditional Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 11/16/2020 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 11/23/2020 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/31/2020 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 12/31/2020 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 12/31/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 1/14/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 1/14/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 1/19/2021 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 1/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/8/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 2/11/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/17/2021 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 2/17/2021 | Approved | THOMAS FINNILA |
| Insulation | 2/17/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 2/17/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 2/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 2/23/2021 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 3/4/2021 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 3/23/2021 | Approved | THOMAS FINNILA |
| Sewer | 5/27/2021 | Approved | THOMAS FINNILA |
| Gas Test | 6/4/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 6/4/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Not Ready | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/29/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/29/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/29/2021 | Approved | THOMAS FINNILA |
| Green Building Final | 6/29/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Not Ready | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2021 | SGSOV Not Ready | DANIEL ORRANTE |
| Smoke Detectors | 7/8/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| ELECTRICAL-Final | 2/9/2022 | No Access for Inspection | CALEB MEISTER |
| HVAC-Final | 2/9/2022 | No Access for Inspection | CALEB MEISTER |
| PLUMBING-Final | 2/9/2022 | No Access for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 2/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 2/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 2/24/2022 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 2/24/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Final | 3/4/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 3/4/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/25/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 3/25/2022 | Approved | THOMAS FINNILA |
| MERV13>=Final | 3/25/2022 | Approved | THOMAS FINNILA |
| Final | 4/6/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 4/6/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 4/6/2022 | Approved | THOMAS FINNILA |
| Final | 4/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | THOMAS FINNILA |
| Special/Order Compliance | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| Final | 4/27/2022 | OK to Issue CofO | DAVID MATSON |