1585 W VERNON AVE 90062
Certificate Information: 1585 W VERNON AVE 90062
- Application / Permit
- 20014-20000-01175
- Plan Check / Job No.
- B20VN04445
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 5'-6" X 10'-0" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 4/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 3/16/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/17/2020 | APPLICANT |
| Plan Check Approved | 3/31/2020 | JEROME MAGAT PALMA |
| Issued | 4/9/2020 | LADBS |
| CofO in Progress | 10/26/2020 | ROBERT MCDOWELL |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
| CofO Issued | 12/10/2020 | DEROLD HAUFF |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/17/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/19/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/22/2020 | Corrections Issued | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/29/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 8/3/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 8/21/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 8/21/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 8/21/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 8/21/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 8/21/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 8/27/2020 | Approved | SABAS ALONSO |
| Shower Pan | 8/27/2020 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 9/1/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 9/1/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 9/1/2020 | Approved | ROBERT MCDOWELL |
| Shower Pan | 9/1/2020 | Approved | ROBERT MCDOWELL |
| Shower Pan | 9/10/2020 | Approved | ROBERT MCDOWELL |
| Final | 10/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 10/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Final | 10/13/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Smoke Detectors | 10/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Final | 10/19/2020 | Approved | ROBERT MCDOWELL |
| Final | 10/19/2020 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 10/19/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 10/19/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 10/19/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 10/19/2020 | Approved | ROBERT MCDOWELL |
| Final | 10/26/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Service/Power Release | 11/24/2020 | Approved | ROBERT MCDOWELL |