5355 E OAKLAND ST Unit 1-5 90032
Certificate Information: 5355 E OAKLAND ST Unit 1-5 90032
- Application / Permit
- 20014-20000-01172
- Plan Check / Job No.
- B20VN04441
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADDITION TO (E) SFD TO MAKE (5) UNITS APT - add 4 unit w/ att. carport and attached to existing dwelling with a covered entrance.
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | SAM CHANG |
| Disabled Access Plans Picked Up | 4/15/2020 | APPLICANT |
| Green Plans Picked Up | 4/15/2020 | APPLICANT |
| Corrections Issued | 4/17/2020 | SAM CHANG |
| Quality Review Completed | 4/28/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/21/2020 | SAM CHANG |
| Applicant returned to address corrections | 10/8/2020 | SAM CHANG |
| Applicant returned to address corrections | 11/13/2020 | SAM CHANG |
| Applicant returned to address corrections | 2/16/2021 | SAM CHANG |
| Applicant returned to address corrections | 2/19/2021 | SAM CHANG |
| Plan Check Approved | 3/17/2021 | SAM CHANG |
| Issued | 4/26/2021 | APPLICANT |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| CofO in Progress | 11/9/2022 | MARK FERRARI |
| CofO Issued | 11/22/2022 | ERNESTO CORRAL |
| Permit Finaled | 11/22/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2020 | JUAN ASHTON |
| Frnt yard landscape/Water mgmt | Cleared | 7/10/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 7/10/2020 | RICHARD REASER |
| Sewer availability | Cleared | 9/1/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 9/29/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2020 | JUAN ASHTON |
| DAS Clearance | Cleared | 10/20/2020 | NORLITO MEDRANO |
| Green Code | Cleared | 10/20/2020 | AARON COSTA |
| Grading Pre-Inspection | Cleared | 12/7/2020 | SAM CHANG |
| Low Impact Development | Cleared | 12/10/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/6/2021 | CECILIO NAVARRO |
| Fire Marshall Fire Life Safety | Cleared | 2/1/2021 | OSCAR SALGADO JR |
| Building over 3-story or 36-ft | Cleared | 2/19/2021 | CALOSHA APPROVED |
Contact Information
| Architect | Azimi,, Babak; Lic. No.: C31944 | 4940 CALVIN AVENUE TARZANA, CA 91356 |
| Contractor | Line Electric Inc; Lic. No.: 910172-B | 4055 WILSHIRE BLVD #506 LOS ANGELES, CA 90010 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 7/23/2021 | Partial Inspection | LANNY MERRICK |
| Special/Order Compliance | 7/26/2021 | Partial Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 8/13/2021 | Not Ready for Inspection | MARK FERRARI |
| Special/Order Compliance | 8/13/2021 | Corrections Issued | MARK FERRARI |
| Special/Order Compliance | 8/20/2021 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 9/23/2021 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 9/29/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 9/29/2021 | Partial Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 10/5/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/6/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 10/22/2021 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | MARK FERRARI |
| Masonry Wall/Backfill | 11/4/2021 | Approved | MARK FERRARI |
| Deputy Reinf. Masonry | 11/5/2021 | Approved | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2021 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 11/10/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/15/2021 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 11/16/2021 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/23/2021 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Not Ready for Inspection | MARK FERRARI |
| Green Building Rough | 11/30/2021 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 11/30/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 11/30/2021 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 12/2/2021 | Conditional Approval | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Partial Inspection | MARK FERRARI |
| Green Building Rough | 1/6/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 1/6/2022 | Corrections Issued | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Partial Inspection | MARK FERRARI |
| Special/Order Compliance | 2/8/2022 | Corrections Issued | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 3/10/2022 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 3/22/2022 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 4/20/2022 | Not Ready for Inspection | NICK DANERI |
| Green Building Rough | 4/26/2022 | Approved | MARK FERRARI |
| Wood Frame | 4/26/2022 | Partial Approval | MARK FERRARI |
| Insulation | 4/29/2022 | Partial Approval | MARK FERRARI |
| Insulation | 5/3/2022 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 5/5/2022 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 5/6/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 5/11/2022 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 5/11/2022 | Corrections Issued | MARK FERRARI |
| Drywall Nailing | 5/17/2022 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 5/17/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 5/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 5/24/2022 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 9/7/2022 | Partial Approval | MARK FERRARI |
| Final | 10/4/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 10/4/2022 | Approved | RAFAEL ESPINOZA |
| Green Building Final | 10/4/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 10/4/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Rec and Parks Fee Memo | 10/4/2022 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 10/4/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 10/7/2022 | Partial Inspection | MARK FERRARI |
| Final | 10/13/2022 | Conditional Approval | MARK FERRARI |
| Green Building Final | 10/13/2022 | Approved | MARK FERRARI |
| Smoke Detectors | 10/13/2022 | Approved | MARK FERRARI |
| Wood Frame | 10/13/2022 | Approved | MARK FERRARI |