3604 S ASHWOOD AVE 90066

Certificate Information: 3604 S ASHWOOD AVE 90066

Application / Permit
20014-20000-01170
Plan Check / Job No.
B20VN04437
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6'-6" x 9' front and 15' x 27' rear addition to the single-family dwelling. Relocate the laundry room and interior remodel per design.
Permit Issued
Issued on 5/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 ANGELICA DAVE
Corrections Issued 3/17/2020 ANGELICA DAVE
Building Plans Picked Up 3/18/2020 APPLICANT
Plan Check Approved 4/28/2020 ANGELICA MARTINEZ
Issued 5/20/2020 LADBS
CofO in Progress 9/23/2022 JESUS RODRIGUEZ
Permit Finaled 9/28/2022 DANIEL ORRANTE
CofO Issued 9/28/2022 DANIEL ORRANTE
Permit Finaled 9/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 4/2/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/20/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/21/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/5/2020 PATRICK MISCHLICH

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Superior Home Builders Inc; Lic. No.: 875933-B 6569 CLEOMOORE AVE      WEST HILLS, CA 91307

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/23/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/28/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/5/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 10/5/2020 Partial Approval ENRIQUE MIRELES
Underground Mechanical 10/5/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/22/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 10/22/2020 Approved ENRIQUE MIRELES
Green Building Rough 10/22/2020 Approved ENRIQUE MIRELES
HVAC-Rough 10/22/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/22/2020 Approved ENRIQUE MIRELES
Wood Frame 10/22/2020 Approved ENRIQUE MIRELES
Insulation 10/23/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 10/26/2020 Approved ENRIQUE MIRELES
Drywall Nailing 10/28/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/4/2020 Approved ENRIQUE MIRELES
Shower Pan 11/4/2020 Approved ENRIQUE MIRELES
Final 3/24/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/24/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/24/2021 Approved ENRIQUE MIRELES
Gas Test 3/25/2021 Approved ENRIQUE MIRELES
Final 4/9/2021 Corrections Issued ENRIQUE MIRELES
Final 5/18/2021 Corrections Issued ENRIQUE MIRELES
Final 9/8/2021 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 5/20/2022 Approved PATRICK QUALEY
HVAC-Final 5/20/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 5/20/2022 Corrections Issued PATRICK QUALEY
Final 9/23/2022 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 9/23/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 9/23/2022 Approved JESUS RODRIGUEZ