2440 N DITMAN AVE 90032

Certificate Information: 2440 N DITMAN AVE 90032

Application / Permit
20014-20000-01160
Plan Check / Job No.
B20VN04396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-0" X 12'-1" ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING FOR RECREATION ROOM WITH 1/2 BATHROOM. WORK PER WFPP.
Permit Issued
Issued on 9/2/2020
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 ROSENDO MEDINA
Corrections Issued 3/12/2020 ROSENDO MEDINA
Plan Check Approved 8/28/2020 ROSENDO MEDINA
Issued 9/2/2020 APPLICANT
CofO in Progress 1/9/2023 AMY COLIN
Permit Finaled 1/10/2023 DEROLD HAUFF
CofO Issued 1/10/2023 DEROLD HAUFF
Permit Finaled 1/10/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/28/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 7/2/2020 WALLIE JONG
"D" conditions Cleared 8/13/2020 JOE LUCKEY
"Q" conditions Cleared 8/13/2020 JOE LUCKEY
Grading Pre-Inspection Cleared 8/28/2020 ROSENDO MEDINA

Contact Information

No Data Available.

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/13/2020 Partial Approval COREY HUPP
Deputy Drilled-In Anchors 11/17/2020 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 11/18/2020 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Partial Approval COREY HUPP
Interior/Exterior Lathing 8/24/2021 Approved RUBEN SALAS
Drywall Nailing 3/31/2022 Corrections Issued AMY COLIN
Drywall Nailing 4/8/2022 Corrections Issued RUBEN SALAS
Insulation 4/8/2022 Corrections Issued RUBEN SALAS
Insulation 4/13/2022 Conditional Approval AMY COLIN
Drywall Nailing 5/11/2022 Approved RUBEN SALAS
BUILDING-Rough-Frame 10/24/2022 Approved AMY COLIN
Green Building Rough 10/24/2022 Approved AMY COLIN
Rough-Elec/Plmb/HVAC 10/24/2022 Approved AMY COLIN
Final 1/3/2023 Partial Inspection AMY COLIN
Footing/Foundation/Slab 1/3/2023 Approved AMY COLIN
Green Building Final 1/3/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Approved AMY COLIN
Smoke Detectors 1/3/2023 Approved AMY COLIN
Final 1/9/2023 OK to Issue CofO AMY COLIN