12775 W WILLARD ST 91605
Certificate Information: 12775 W WILLARD ST 91605
- Application / Permit
- 20014-20000-01130
- Plan Check / Job No.
- B20VN04274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION of (33'-8"X15'-2" )TO (E) AND CONVERSION of GARAGE (E) 20'-3"x18'-2"TO ACCESSORY DWELLING UNIT (E) WALL (20'-3") AND FOOTNG TO REMAIN NEXT TO PL
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Green Plans Picked Up | 3/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/8/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/16/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/8/2020 | APPLICANT |
| Plan Check Approved | 12/17/2020 | MOHAMMAD ESMAILI |
| Issued | 12/17/2020 | APPLICANT |
| CofO in Progress | 8/31/2021 | GREGG CUMMINGS |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/3/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 6/25/2020 | KURT CORRAL |
| Construction near power lines | Cleared | 8/17/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/15/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 12/2/2020 | DAVID MATSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2021 | Partial Approval | GREGG CUMMINGS |
| Sewer | 2/8/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/16/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/19/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/23/2021 | Approved | GREGG CUMMINGS |
| Wood Frame | 3/9/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 4/6/2021 | Approved | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 4/7/2021 | Partial Approval | BEAU COLLINS |
| Wood Frame | 4/7/2021 | Partial Approval | BEAU COLLINS |
| Underground Mechanical | 4/15/2021 | Approved | GREGG CUMMINGS |
| Shower Pan | 4/20/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/26/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/26/2021 | Approved | GREGG CUMMINGS |
| MERV13>=Rough | 4/26/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 4/26/2021 | Approved | GREGG CUMMINGS |
| Insulation | 4/29/2021 | Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 4/29/2021 | Partial Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 5/3/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/10/2021 | Approved | GREGG CUMMINGS |
| Final | 7/22/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/22/2021 | Approved | GREGG CUMMINGS |
| Green Building Final | 7/22/2021 | Approved | GREGG CUMMINGS |
| MERV13>=Final | 7/22/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 7/22/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/31/2021 | Approved | GREGG CUMMINGS |
| Final | 8/31/2021 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 8/31/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/31/2021 | Approved | GREGG CUMMINGS |