11114 N PARR AVE 91040
Certificate Information: 11114 N PARR AVE 91040
- Application / Permit
- 20014-20000-01110
- Plan Check / Job No.
- B20VN04218
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18'-1" X 20'-2" (E) DETACHED GARAGE AND ADD 15'-6" X 20'-2" & 8' X 9'-2" INTO (N) ACCESSODRY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2020 | ROSENDO MEDINA |
| Corrections Issued | 3/12/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 1/19/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 9/3/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| Issued | 9/13/2021 | APPLICANT |
| CofO in Progress | 4/19/2023 | WILLIAM WREN |
| CofO Issued | 4/20/2023 | MICHAEL SMITH |
| Permit Finaled | 4/20/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/30/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/30/2020 | RIDWAN HARDY |
| Address approval | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 12/7/2020 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 12/25/2020 | JEREMY CARTER |
| GPI Written Notices | Cleared | 1/15/2021 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2022 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/27/2022 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 11/3/2022 | Conditional Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/4/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Approved | WILLIAM WREN |
| Final | 12/16/2022 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 12/16/2022 | Approved | WILLIAM WREN |
| HVAC-Rough | 1/9/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 1/9/2023 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 1/13/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 1/13/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 1/13/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 1/13/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 1/18/2023 | Approved | WILLIAM WREN |
| Insulation | 1/18/2023 | Approved | WILLIAM WREN |
| Shower Pan | 1/18/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 1/23/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 1/30/2023 | Approved | WILLIAM WREN |
| Final | 4/3/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 4/3/2023 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 4/3/2023 | Approved | WILLIAM WREN |
| Final | 4/18/2023 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 4/18/2023 | Approved | WILLIAM WREN |