1195 N TOWER GROVE DR 90210
Certificate Information: 1195 N TOWER GROVE DR 90210
- Application / Permit
- 20014-20000-01091
- Plan Check / Job No.
- B20VN04172
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20'-0" X 29'-6" IRREG SHAPED ADDITION FOR NEW DINING ROOM AND FOYER. 3'-0" X 12'-6" IRREG SHAPED ADDITION TO ENLARGE AND REMODEL KITCHEN.
- Permit Issued
- Issued on 6/18/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 3/30/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 4/3/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/8/2020 | APPLICANT |
| Green Plans Picked Up | 4/8/2020 | APPLICANT |
| Plan Check Approved | 6/3/2020 | JEROME MAGAT PALMA |
| Issued | 6/18/2020 | LADBS |
| CofO in Progress | 10/19/2021 | CARLOS MATAMOROS |
| Permit Finaled | 11/19/2021 | DEROLD HAUFF |
| CofO Issued | 11/19/2021 | DEROLD HAUFF |
| Permit Finaled | 11/19/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 4/16/2020 | LAUREN PADICK |
| ZA Case | Cleared | 4/16/2020 | LAUREN PADICK |
| BHO/Hillside ordinance | Cleared | 4/30/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/30/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/30/2020 | DINAH GARIN |
| Sewer availability | Cleared | 4/30/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/4/2020 | DINAH GARIN |
| GPI Written Notices | Cleared | 5/5/2020 | TIMOTHY POWELL |
| Grading Pre-Inspection | Cleared | 5/14/2020 | BRIAN MILLER |
| Green Code | Cleared | 5/27/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Angel'S Construction; Lic. No.: 750823-B | 18560 VANOWEN ST #31 RESEDA, CA 91335 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/24/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 7/9/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/9/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 9/1/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Drilled-In Anchors | 9/10/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Insulation | 10/16/2020 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 10/21/2020 | Approved | ANTHONY MCDOWALL |
| Shower Pan | 10/22/2020 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 11/30/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 12/9/2020 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 5/4/2021 | Approved | ANTHONY MCDOWALL |
| Final | 5/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 5/4/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 5/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Green Building Rough | 5/4/2021 | Approved | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Not Ready | ANTHONY MCDOWALL |
| Smoke Detectors | 5/4/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 5/18/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Final | 5/18/2021 | Approved | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Not Ready | ANTHONY MCDOWALL |
| Final | 8/16/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Final | 8/16/2021 | Approved | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Not Ready | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 8/31/2021 | Approved | CARLOS MATAMOROS |
| Final | 8/31/2021 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Final | 8/31/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 8/31/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV Approved | CARLOS MATAMOROS |