11972 W NEENACH ST 91352
Certificate Information: 11972 W NEENACH ST 91352
- Application / Permit
- 20014-20000-01087
- Plan Check / Job No.
- B20VN04154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 19' 3" X 16' TO REAR OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 12/2/2020
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | GURUNATH NESARAJAH |
| Green Plans Picked Up | 3/27/2020 | APPLICANT |
| Corrections Issued | 4/2/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 4/3/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/8/2020 | APPLICANT |
| Plan Check Approved | 6/18/2020 | GURUNATH NESARAJAH |
| Issued | 12/2/2020 | APPLICANT |
| CofO in Progress | 3/10/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 6/15/2022 | DANIEL ORRANTE |
| CofO Issued | 6/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 5/5/2020 | DAVID MATSON |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/6/2020 | GUILLERMO PETRA |
| Clean Up Green Up | Cleared | 5/7/2020 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 6/2/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/10/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | 610 ILEX STREET SAN FERNANDO, CA 91340 |
| Engineer | Samadzadeh,, Ali Reza; Lic. No.: C87661 | 20655 SHERMAN WAY #5 LOS ANGELES, CA 91306 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 6/11/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 6/11/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 6/11/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/8/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 7/16/2021 | Approved | JOHN HAYES |
| Green Building Rough | 7/16/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 7/16/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/16/2021 | Partial Approval | JOHN HAYES |
| MERV13>=Rough | 7/16/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 7/28/2021 | Approved | AMY COLIN |
| ELECTRICAL-Final | 9/7/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 9/16/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 12/3/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 12/3/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 12/3/2021 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 12/3/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 1/19/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/19/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/19/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/19/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 2/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/18/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Final | 3/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/10/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 3/10/2022 | Approved | CHRISTOPHER DELLEFIELD |