6443 N CLYBOURN AVE 91606
Certificate Information: 6443 N CLYBOURN AVE 91606
- Application / Permit
- 20014-20000-01077
- Plan Check / Job No.
- B20VN04134
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 23' X 34'-11" STORAGE & 20'-1" X 20'-6" GARAGE AND ADD (4'-8" X 20'-1") IRREGULAR SHAPE TO CREATE (N) ACCESSORY DWELLING UNIT. CONVERT 6' X 20'-1" PORTION OF GARAGE TO STORAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2020 | RAPHAEL ROSAS |
| Corrections Issued | 3/10/2020 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/2/2020 | APPLICANT |
| Applicant returned to address corrections | 6/17/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 7/14/2020 | RAPHAEL ROSAS |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 2/3/2022 | THOMAS FINNILA |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/13/2020 | RIDWAN HARDY |
| Address approval | Cleared | 6/2/2020 | ADRIAN CASTRO |
| Permit | Cleared | 6/2/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/2/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/4/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/25/2020 | Not Ready for Inspection | DANIEL DREW |
| Pre-Inspection | 9/25/2020 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 2/5/2021 | Not Ready for Inspection | DANIEL DREW |
| Underground Mechanical | 2/5/2021 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 4/7/2021 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 4/7/2021 | Not Ready for Inspection | BEAU COLLINS |
| HVAC-Rough | 4/7/2021 | Corrections Issued | BEAU COLLINS |
| ELECTRICAL-Rough | 4/14/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 4/14/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Approved | DANIEL DREW |
| Green Building Rough | 4/22/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 4/22/2021 | Approved | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 4/22/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 5/7/2021 | Approved | MISAEL ESPARZA |
| Green Building Final | 5/7/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 5/7/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/7/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 5/13/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 5/19/2021 | Approved | ARAM AVEDISIAN |
| Shower Pan | 6/16/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/8/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 9/20/2021 | Corrections Issued | DANIEL DREW |
| Final | 9/20/2021 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 9/20/2021 | Approved | DANIEL DREW |
| Green Building Final | 9/20/2021 | Corrections Issued | DANIEL DREW |
| HVAC-Final | 9/20/2021 | Corrections Issued | DANIEL DREW |
| PLUMBING-Final | 9/20/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 9/20/2021 | Corrections Issued | DANIEL DREW |
| ELECTRICAL-Final | 9/30/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 9/30/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Final | 9/30/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Final | 9/30/2021 | Approved | DANIEL DREW |
| Smoke Detectors | 9/30/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 10/13/2021 | Approved | DANIEL DREW |
| Final | 11/1/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 11/1/2021 | Approved | DANIEL DREW |
| HVAC-Final | 11/1/2021 | Approved | DANIEL DREW |
| Final | 11/24/2021 | Partial Approval | JENNIFER RABUCHIN |
| Final | 2/2/2022 | OK to Issue CofO | THOMAS FINNILA |