13747 1/2 W JUDD ST 91331

Certificate Information: 13747 1/2 W JUDD ST 91331

Application / Permit
20014-20000-01070
Plan Check / Job No.
B20VN04109
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 12' X 18' DETACHED STORAGE BUILDING AND ADD 6' X 18' AND 8' X 18' FOR NEW ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER WFPP.
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 2/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/18/2020 JENNIFER LEE
Corrections Issued 3/18/2020 JENNIFER LEE
Applicant returned to address corrections 11/24/2020 JENNIFER LEE
Plan Check Approved 5/25/2021 JENNIFER LEE
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/26/2021 APPLICANT
CofO in Progress 12/23/2021 MICHEL ABAJAN
Permit Finaled 2/12/2022 MICHAEL SMITH
CofO Issued 2/12/2022 MICHAEL SMITH
Permit Finaled 2/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/15/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/15/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 5/13/2021 WALTER RAMIREZ
Construction within easement Cleared 5/13/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/18/2021 ADRIAN CASTRO
Sewer availability Cleared 5/18/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2021 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 8/26/2021 Approved MICHEL ABAJAN
Underground Mechanical 8/26/2021 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 9/3/2021 No Access for Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 9/7/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 9/14/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/28/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 9/29/2021 No Access for Inspection JOHN HAYES
METHANE-Rough 9/29/2021 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/18/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/18/2021 Approved MICHEL ABAJAN
Green Building Rough 10/18/2021 Approved MICHEL ABAJAN
METHANE-Rough 10/18/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 10/18/2021 Approved MICHEL ABAJAN
Insulation 10/21/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/21/2021 Approved MICHEL ABAJAN
Drywall Nailing 10/25/2021 Approved MICHEL ABAJAN
Shower Pan 10/27/2021 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 10/29/2021 Approved MICHEL ABAJAN
Final 12/2/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 12/2/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 12/2/2021 Not Ready for Inspection JOHN HAYES
METHANE-Barrier 12/2/2021 Not Ready for Inspection JOHN HAYES
METHANE-Subgrade 12/2/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 12/2/2021 Approved JOHN HAYES
Final 12/10/2021 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 12/10/2021 Approved MICHEL ABAJAN
Green Building Final 12/10/2021 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 12/10/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 12/10/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved MICHEL ABAJAN
Final 12/23/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 12/23/2021 Approved MICHEL ABAJAN