8128 S NAYLOR AVE 90045

Certificate Information: 8128 S NAYLOR AVE 90045

Application / Permit
20014-20000-01066
Plan Check / Job No.
B20VN04100
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD & ATTACH (11'-0"x 14'-0") STORAGE RM AND ADD ( 2'-0"x 14'-0") & CONVERT (E) DET. 2- CAR GARAGE TO ACCESSORY DWELLING UNIT. WORK PER ENGINEER.
Permit Issued
Issued on 5/13/2020
Issuing Office
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/9/2020 TROY DEGUZMAN
Corrections Issued 3/9/2020 TROY DEGUZMAN
Building Plans Picked Up 3/10/2020 APPLICANT
Plan Check Approved 5/12/2020 TROY DEGUZMAN
Issued 5/13/2020 APPLICANT
CofO in Progress 11/15/2021 RICHARD STEINBACH
Permit Finaled 11/19/2021 DANIEL ORRANTE
CofO Issued 11/19/2021 DANIEL ORRANTE
Permit Finaled 11/19/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/13/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 3/13/2020 JOHN LIN
Roof/Waste drainage to street Cleared 3/13/2020 JOHN LIN
Sewer availability Cleared 3/13/2020 JOHN LIN
Construction near power lines Cleared 4/23/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2020 Approved JUAN VALENZUELA
Underground Mechanical 6/22/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/1/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 7/14/2020 Approved JUAN VALENZUELA
Deputy Wood Construction 7/20/2020 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 7/20/2020 Not Ready for Inspection JUAN VALENZUELA
Sewer 7/20/2020 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 7/21/2020 Partial Approval JUAN VALENZUELA
Sewer 7/21/2020 Approved JUAN VALENZUELA
Underground Mechanical 7/21/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/22/2020 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 7/23/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 7/23/2020 Approved JUAN VALENZUELA
Green Building Rough 7/23/2020 Approved JUAN VALENZUELA
HVAC-Rough 7/23/2020 Approved JUAN VALENZUELA
Insulation 7/23/2020 Approved JUAN VALENZUELA
Drywall Nailing 7/27/2020 Approved JUAN VALENZUELA
Green Building Rough 7/27/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/27/2020 Approved JUAN VALENZUELA
Final 10/4/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 10/4/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 10/4/2021 Approved BRENDAN LOONEY
Final 10/21/2021 Not Ready for Inspection DAVID FEILER
Green Building Final 10/21/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 11/2/2021 Corrections Issued RICHARD STEINBACH
Final 11/2/2021 Not Ready for Inspection RICHARD STEINBACH
Green Building Final 11/2/2021 Approved RICHARD STEINBACH
HVAC-Final 11/2/2021 Corrections Issued RICHARD STEINBACH
PLUMBING-Final 11/2/2021 Corrections Issued RICHARD STEINBACH
ELECTRICAL-Final 11/12/2021 Approved RICHARD STEINBACH
Final 11/12/2021 OK to Issue CofO RICHARD STEINBACH
Gas Test 11/12/2021 Approved RICHARD STEINBACH
HVAC-Final 11/12/2021 Approved RICHARD STEINBACH
PLUMBING-Final 11/12/2021 Approved RICHARD STEINBACH
Service/Power Release 11/12/2021 Approved RICHARD STEINBACH