15038 W BASSETT ST 91405

Certificate Information: 15038 W BASSETT ST 91405

Application / Permit
20014-20000-01047
Plan Check / Job No.
B20VN04029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION of (E) garage and ADDITION to create an irregular 34'2" x 35'6" (1,010 SF) Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 10/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2020 APPLICANT
Green Plans Picked Up 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 LUIS RINCON
Corrections Issued 3/25/2020 LUIS RINCON
Quality Review Completed 3/25/2020 CHON CHIO KUO
Building Plans Picked Up 4/2/2020 APPLICANT
Plan Check Approved 10/30/2020 LUIS RINCON
Issued 10/30/2020 APPLICANT
CofO in Progress 8/3/2022 RICHARD DOCKUS
Permit Finaled 8/5/2022 RONALD MYRICK
CofO Issued 8/5/2022 RONALD MYRICK
Permit Finaled 8/5/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 4/9/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/15/2020 LEE GUILBEAUX
Green Code Cleared 4/17/2020 AARON COSTA
Hydrant and Access approval Cleared 5/4/2020 MATTHEW CRAIG
Sewer availability Cleared 6/11/2020 GABRIEL ROBLES
Low Impact Development Cleared 8/6/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 8/11/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2021 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 7/26/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 7/26/2021 Partial Approval WILLIAM KUEHN
BUILDING-Rough-Frame 8/18/2021 Partial Approval RICHARD DOCKUS
Sewer 8/18/2021 Approved RICHARD DOCKUS
ELECTRICAL-Rough 10/29/2021 Approved ALAN MORELOS
HVAC-Rough 10/29/2021 Approved ALAN MORELOS
BUILDING-Rough-Frame 11/5/2021 Corrections Issued RICHARD DOCKUS
Green Building Rough 11/5/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 11/5/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 11/17/2021 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 11/17/2021 Approved RICHARD DOCKUS
HVAC-Rough 11/17/2021 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 11/17/2021 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 11/30/2021 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 11/30/2021 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 2/3/2022 Approved RICHARD DOCKUS
Insulation 2/11/2022 Approved ALAN MORELOS
Drywall Nailing 2/16/2022 Approved ALAN MORELOS
Underground Mechanical 2/16/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 2/22/2022 Approved RYAN SALAZAR
Underground Mechanical 2/22/2022 Approved RYAN SALAZAR
Final 6/15/2022 Corrections Issued MATT KELLERMAN
Green Building Final 6/15/2022 Corrections Issued MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 6/15/2022 Approved MATT KELLERMAN
Final 6/23/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 6/23/2022 Approved RICHARD DOCKUS
Final 7/20/2022 Conditional Approval RICHARD DOCKUS
Final 8/2/2022 OK to Issue CofO RICHARD DOCKUS