10451 N SHARP AVE 91331
Certificate Information: 10451 N SHARP AVE 91331
- Application / Permit
- 20014-20000-01036
- Plan Check / Job No.
- B20VN03959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 7'-6" x 36'-2" attached patio cover per LA city detail.
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | ANGELICA DAVE |
| Plan Check Approved | 3/5/2020 | ANGELICA MARTINEZ |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 10/26/2020 | CHRISTOPHE COCHRAN |
| CofO in Progress | 10/26/2020 | CHRISTOPHE COCHRAN |
| CofO Issued | 9/30/2021 | MICHAEL SMITH |
| Permit Finaled | 9/30/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 3/19/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 3/19/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/24/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 3/24/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/6/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/6/2020 | Approved | JENNIFER RABUCHIN |
| Final | 4/6/2020 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/6/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/6/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/6/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 4/6/2020 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 9/30/2021 | Approved | JENNIFER RABUCHIN |