11626 W CANTARA ST 91605

Certificate Information: 11626 W CANTARA ST 91605

Application / Permit
20014-20000-01025
Plan Check / Job No.
B20VN03926
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ATTACHED PATIO COVER ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/6/2020 YAQUB MIRZA
Plan Check Approved 3/6/2020 YAQUB MIRZA
Issued 3/6/2020 LADBS
CofO in Progress 10/25/2023 DAVID ANDERSON
CofO in Progress 12/8/2023 DAVID ANDERSON
CofO in Progress 2/28/2024 DAVID ANDERSON
Permit Finaled 3/4/2024 RUBEN SALAS
CofO Issued 3/4/2024 RUBEN SALAS
Permit Finaled 3/4/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 3/5/2020 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 3/6/2020 JOHN LIN
Roof/Waste drainage to street Cleared 3/6/2020 JOHN LIN
Public Works-Highway Ded. Cleared 3/6/2020 JOHN LIN
Public Works-Open Permits Cleared 3/6/2020 JOHN LIN
Public Works-Sewers Cleared 3/6/2020 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/24/2020 Approved JOHN HAYES
Footing/Foundation/Slab 8/4/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 8/21/2020 Not Ready for Inspection MATTHEW NELSON
METHANE-Barrier 8/21/2020 Not Ready for Inspection MATTHEW NELSON
METHANE-Subgrade 8/21/2020 Not Ready for Inspection MATTHEW NELSON
Deputy Drilled-In Anchors 12/7/2020 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 12/7/2020 Not Ready for Inspection JOHN HAYES
METHANE-Barrier 12/7/2020 Not Ready for Inspection JOHN HAYES
METHANE-Subgrade 12/7/2020 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 12/11/2020 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 12/28/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/24/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/24/2021 Not Ready for Inspection JOHN HAYES
METHANE-Rough 5/24/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/24/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/19/2023 Corrections Issued MATTHEW NELSON
Final 1/19/2023 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 1/19/2023 Approved MATTHEW NELSON
METHANE-Barrier 1/19/2023 Approved MATTHEW NELSON
METHANE-Final 1/19/2023 Not Ready for Inspection MATTHEW NELSON
METHANE-Rough 1/19/2023 Approved MATTHEW NELSON
METHANE-Subgrade 1/19/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 1/19/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/30/2023 Approved DAVID ANDERSON
Final 8/30/2023 Corrections Issued DAVID ANDERSON
METHANE-Final 8/30/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved DAVID ANDERSON
Final 9/25/2023 Not Ready for Inspection DAVID ANDERSON
Drywall Nailing 10/18/2023 Approved WILLIAM WREN
Final 10/23/2023 OK to Issue CofO DAVID ANDERSON
Final 12/22/2023 Corrections Issued DAVID ANDERSON