12930 W DEWEY ST 90066

Certificate Information: 12930 W DEWEY ST 90066

Application / Permit
20014-20000-01016
Plan Check / Job No.
B20VN03908
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING (30'-8" x 23'-8" IRR. SHAPE) AND MAJOR REMODEL.
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
CofO Issued on 7/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SEAN SHAHMIRI
Corrections Issued 3/5/2020 SEAN SHAHMIRI
Building Plans Picked Up 3/9/2020 APPLICANT
Applicant returned to address corrections 6/5/2020 SEAN SHAHMIRI
Plan Check Approved 6/17/2020 SEAN SHAHMIRI
Issued 7/16/2020 APPLICANT
CofO in Progress 7/8/2021 ENRIQUE MIRELES
CofO Issued 7/21/2021 VINCENT COTTON
Permit Finaled 7/21/2021 VINCENT COTTON

Permit Application Clearance Information

Construction near power lines Cleared 3/11/2020 OSCAR CASTRO
Sewer availability Cleared 3/11/2020 THOMAS LANG
Low Impact Development Cleared 6/2/2020 ANDRES COVARRUBIAS
Grading Pre-Inspection Cleared 6/5/2020 SEAN SHAHMIRI
Eng Process Fee Ord 176,300 Cleared 6/9/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 6/9/2020 DINAH GARIN

Contact Information

Contractor Dellergo Development & Construction; Lic. No.: 882785-B 244 REDONDO AVENUE      LONG BEACH, CA 90803
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/24/2020 Approved JOHNNY MIRANDA
Sewer 8/17/2020 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/19/2020 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Partial Approval CRAIG DAVIS
Insulation 8/26/2020 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 11/20/2020 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 11/20/2020 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 11/30/2020 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 11/30/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Corrections Issued JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 12/2/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 No Access for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/7/2020 No Access for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 12/10/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/10/2020 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/10/2020 Partial Approval ENRIQUE MIRELES
Deputy Wood Construction 12/18/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/21/2020 Approved ENRIQUE MIRELES
Green Building Rough 12/21/2020 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/31/2020 Approved ENRIQUE MIRELES
Drywall Nailing 1/5/2021 Corrections Issued PIERRE VEGA
Insulation 1/5/2021 Not Ready for Inspection PIERRE VEGA
Insulation 1/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Insulation 1/7/2021 Approved ENRIQUE MIRELES
Drywall Nailing 1/14/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Not Ready ENRIQUE MIRELES
Final 4/21/2021 No Access for Inspection ENRIQUE MIRELES
Green Building Final 4/21/2021 No Access for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 4/21/2021 No Access for Inspection ENRIQUE MIRELES
Final 4/23/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/23/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/23/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 5/14/2021 Corrections Issued ENRIQUE MIRELES
Smoke Detectors 5/14/2021 Approved ENRIQUE MIRELES
Final 7/8/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 7/8/2021 Approved ENRIQUE MIRELES