12930 W DEWEY ST 90066
Certificate Information: 12930 W DEWEY ST 90066
- Application / Permit
- 20014-20000-01016
- Plan Check / Job No.
- B20VN03908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING (30'-8" x 23'-8" IRR. SHAPE) AND MAJOR REMODEL.
- Permit Issued
- Issued on 7/16/2020
- Issuing Office
- Current Status
- CofO Issued on 7/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SEAN SHAHMIRI |
| Corrections Issued | 3/5/2020 | SEAN SHAHMIRI |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Applicant returned to address corrections | 6/5/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 6/17/2020 | SEAN SHAHMIRI |
| Issued | 7/16/2020 | APPLICANT |
| CofO in Progress | 7/8/2021 | ENRIQUE MIRELES |
| CofO Issued | 7/21/2021 | VINCENT COTTON |
| Permit Finaled | 7/21/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/11/2020 | OSCAR CASTRO |
| Sewer availability | Cleared | 3/11/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 6/2/2020 | ANDRES COVARRUBIAS |
| Grading Pre-Inspection | Cleared | 6/5/2020 | SEAN SHAHMIRI |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/9/2020 | DINAH GARIN |
Contact Information
| Contractor | Dellergo Development & Construction; Lic. No.: 882785-B | 244 REDONDO AVENUE LONG BEACH, CA 90803 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/24/2020 | Approved | JOHNNY MIRANDA |
| Sewer | 8/17/2020 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 8/19/2020 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2020 | Partial Approval | CRAIG DAVIS |
| Insulation | 8/26/2020 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/20/2020 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2020 | Not Ready for Inspection | KENNETH NAGLE |
| HVAC-Rough | 11/20/2020 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 11/30/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 11/30/2020 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 12/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/7/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 12/10/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/10/2020 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/10/2020 | Partial Approval | ENRIQUE MIRELES |
| Deputy Wood Construction | 12/18/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/21/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/21/2020 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/31/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/5/2021 | Corrections Issued | PIERRE VEGA |
| Insulation | 1/5/2021 | Not Ready for Inspection | PIERRE VEGA |
| Insulation | 1/6/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 1/7/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/14/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 4/21/2021 | No Access for Inspection | ENRIQUE MIRELES |
| Green Building Final | 4/21/2021 | No Access for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 4/21/2021 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 4/23/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/23/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 4/23/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 5/14/2021 | Corrections Issued | ENRIQUE MIRELES |
| Smoke Detectors | 5/14/2021 | Approved | ENRIQUE MIRELES |
| Final | 7/8/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 7/8/2021 | Approved | ENRIQUE MIRELES |