10503 W KLING ST 91602

Certificate Information: 10503 W KLING ST 91602

Application / Permit
20014-20000-01003
Plan Check / Job No.
B20VN03854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
33'-6" X 22'-4" IRREGULAR SHAPED ADDITION TO (E) RECROOM TO CONVERT TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 7/8/2021
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ARTIN ZARUKIAN
Corrections Issued 3/21/2020 ARTIN ZARUKIAN
Quality Review Completed 3/24/2020 STEVEN KIM
Green Plans Picked Up 3/24/2020 APPLICANT
Applicant returned to address corrections 4/19/2021 ARTIN ZARUKIAN
Building Plans Picked Up 4/21/2021 APPLICANT
Plan Check Approved 7/8/2021 ARTIN ZARUKIAN
Issued 7/8/2021 APPLICANT
CofO in Progress 7/9/2024 JOSE AVILA
Permit Finaled 7/31/2024 RUBEN SALAS
CofO Issued 7/31/2024 RUBEN SALAS
Permit Finaled 7/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/15/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 ADRIAN CASTRO
Sewer availability Cleared 1/20/2021 ADRIAN CASTRO
Low Impact Development Cleared 5/21/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/26/2021 GABRIEL ROBLES
Green Code Cleared 7/6/2021 AARON COSTA

Contact Information

Architect Duffy,, Robert K; Lic. No.: C7604 11333 MOORPARK ST. #455      TOLUCA LAKE, CA 91602
Contractor Mersola Construction Inc; Lic. No.: 372249-B 444 IRVING DRIVE      BURBANK, CA 91504
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/13/2021 Not Ready for Inspection DANIEL DREW
PLUMBING-Rough 7/13/2021 Partial Approval DANIEL DREW
Pre-Inspection 7/13/2021 Approved DANIEL DREW
Excavation/Setback/Form/Re-Bar 7/19/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 7/19/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 7/22/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 9/2/2021 Approved DANIEL DREW
ELECTRICAL-Rough 9/2/2021 Approved DANIEL DREW
Green Building Rough 9/2/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 9/2/2021 Not Ready for Inspection DANIEL DREW
MERV13>=Rough 9/2/2021 Approved DANIEL DREW
PLUMBING-Rough 9/2/2021 Approved DANIEL DREW
Green Building Rough 9/9/2021 Approved DANIEL DREW
Interior/Exterior Lathing 9/21/2021 Partial Approval JENNIFER RABUCHIN
Insulation 10/1/2021 Approved DANIEL DREW
Drywall Nailing 10/20/2021 Approved DANIEL DREW
Interior/Exterior Lathing 11/15/2021 Partial Approval CALEB MEISTER
Shower Pan 11/15/2021 Conditional Approval CALEB MEISTER
ELECTRICAL-Final 6/17/2024 Corrections Issued JOSE AVILA
Green Building Final 6/17/2024 Approved JOSE AVILA
HVAC-Final 6/17/2024 Corrections Issued JOSE AVILA
MERV13>=Final 6/17/2024 Approved JOSE AVILA
PLUMBING-Final 6/17/2024 Approved JOSE AVILA
Final 7/2/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 7/2/2024 Approved JOSE AVILA
Final 7/8/2024 OK to Issue CofO JOSE AVILA