10501 W KLING ST 91602

Certificate Information: 10501 W KLING ST 91602

Application / Permit
20014-20000-01002
Plan Check / Job No.
B20VN03854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 18'-0" x 17'-6" PATIO ADDITION, 50'-0" X 22'-8" TWO CAR GARAGE /PATIO ADDITION & 4'-0" X 17'-4" & 5'-0" X 11'-8" ADDITION AT 1ST FLOOR, 45'-6" X 20'-4" ADDITION AT 2ND FLOOR TO (E) SFD.
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ARTIN ZARUKIAN
Corrections Issued 3/21/2020 ARTIN ZARUKIAN
Quality Review Completed 3/24/2020 STEVEN KIM
Green Plans Picked Up 3/24/2020 APPLICANT
Applicant returned to address corrections 4/19/2021 ARTIN ZARUKIAN
Building Plans Picked Up 4/21/2021 APPLICANT
Plan Check Approved 1/24/2022 ARTIN ZARUKIAN
Issued 3/2/2022 APPLICANT
CofO in Progress 7/16/2024 JOSE AVILA
Permit Finaled 7/31/2024 RUBEN SALAS
CofO Issued 7/31/2024 RUBEN SALAS
Permit Finaled 7/31/2024 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 9/17/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/20/2021 CARLOS AGUILERA
Low Impact Development Cleared 11/19/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 12/20/2021 CARLOS AGUILERA
Green Code Cleared 1/11/2022 AARON COSTA

Contact Information

Architect Duffy,, Robert K; Lic. No.: C7604 11333 MOORPARK ST. #455      TOLUCA LAKE, CA 91602
Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/19/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 8/25/2022 Not Ready for Inspection JOHN HAYES
Sewer 8/25/2022 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 8/30/2022 Conditional Approval ALAN MORELOS
Footing/Foundation/Slab 9/1/2022 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 9/2/2022 Not Ready for Inspection JOHN HAYES
Deputy Reinf. Concrete 9/6/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 10/7/2022 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/7/2022 Partial Approval JOHN HAYES
Underground Mechanical 10/7/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval JOHN HAYES
Interior/Exterior Lathing 5/3/2023 Partial Approval JOHN HAYES
Special/Order Compliance 6/28/2023 Partial Approval ROBERT GOLD
Verify Sprinkler Sign Off 8/4/2023 Approved DAVID MATSON
Insulation 8/14/2023 Approved JACK KARGODORIAN
Gas Test 1/11/2024 Approved JOHN HAYES
ELECTRICAL-Final 6/17/2024 Corrections Issued JOSE AVILA
Green Building Final 6/17/2024 Approved JOSE AVILA
HVAC-Final 6/17/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 6/17/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 6/27/2024 Approved JOSE AVILA
Drywall Nailing 6/27/2024 Approved JOSE AVILA
ELECTRICAL-Final 6/27/2024 Approved JOSE AVILA
Final 6/27/2024 Corrections Issued JOSE AVILA
Green Building Rough 6/27/2024 Approved JOSE AVILA
HVAC-Final 6/27/2024 Approved JOSE AVILA
MERV13>=Final 6/27/2024 Approved JOSE AVILA
MERV13>=Rough 6/27/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 6/27/2024 Approved JOSE AVILA
Final 7/16/2024 OK to Issue CofO JOSE AVILA