10501 W KLING ST 91602
Certificate Information: 10501 W KLING ST 91602
- Application / Permit
- 20014-20000-01002
- Plan Check / Job No.
- B20VN03854
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 18'-0" x 17'-6" PATIO ADDITION, 50'-0" X 22'-8" TWO CAR GARAGE /PATIO ADDITION & 4'-0" X 17'-4" & 5'-0" X 11'-8" ADDITION AT 1ST FLOOR, 45'-6" X 20'-4" ADDITION AT 2ND FLOOR TO (E) SFD.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 3/21/2020 | ARTIN ZARUKIAN |
| Quality Review Completed | 3/24/2020 | STEVEN KIM |
| Green Plans Picked Up | 3/24/2020 | APPLICANT |
| Applicant returned to address corrections | 4/19/2021 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/21/2021 | APPLICANT |
| Plan Check Approved | 1/24/2022 | ARTIN ZARUKIAN |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 7/16/2024 | JOSE AVILA |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
| CofO Issued | 7/31/2024 | RUBEN SALAS |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/17/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 11/19/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 1/11/2022 | AARON COSTA |
Contact Information
| Architect | Duffy,, Robert K; Lic. No.: C7604 | 11333 MOORPARK ST. #455 TOLUCA LAKE, CA 91602 |
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 8/25/2022 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 8/25/2022 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 8/30/2022 | Conditional Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 9/1/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/2/2022 | Not Ready for Inspection | JOHN HAYES |
| Deputy Reinf. Concrete | 9/6/2022 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/7/2022 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/7/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 10/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 5/3/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 6/28/2023 | Partial Approval | ROBERT GOLD |
| Verify Sprinkler Sign Off | 8/4/2023 | Approved | DAVID MATSON |
| Insulation | 8/14/2023 | Approved | JACK KARGODORIAN |
| Gas Test | 1/11/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 6/17/2024 | Corrections Issued | JOSE AVILA |
| Green Building Final | 6/17/2024 | Approved | JOSE AVILA |
| HVAC-Final | 6/17/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 6/17/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 6/27/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/27/2024 | Approved | JOSE AVILA |
| Final | 6/27/2024 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 6/27/2024 | Approved | JOSE AVILA |
| HVAC-Final | 6/27/2024 | Approved | JOSE AVILA |
| MERV13>=Final | 6/27/2024 | Approved | JOSE AVILA |
| MERV13>=Rough | 6/27/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 6/27/2024 | Approved | JOSE AVILA |
| Final | 7/16/2024 | OK to Issue CofO | JOSE AVILA |