3305 W 59TH PL 90043

Certificate Information: 3305 W 59TH PL 90043

Application / Permit
20014-20000-01001
Plan Check / Job No.
B20VN03839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-0" X 10'-9" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (615 SQ FT).
Permit Issued
Issued on 3/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/4/2020 JEROME MAGAT PALMA
Corrections Issued 3/4/2020 JEROME MAGAT PALMA
Plan Check Approved 3/11/2020 JEROME MAGAT PALMA
Issued 3/11/2020 LADBS
CofO in Progress 9/21/2020 FREDDIE RIVERA
Permit Finaled 9/27/2020 DEROLD HAUFF
CofO Issued 9/27/2020 DEROLD HAUFF
Permit Finaled 9/27/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/4/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/4/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 3/4/2020 GABRIEL ROBLES
Sewer availability Cleared 3/4/2020 GABRIEL ROBLES
Construction near power lines Cleared 3/5/2020 OSCAR CASTRO

Contact Information

Contractor Excel Construction L A Inc; Lic. No.: 998499-B 7100 VAN NUYS BOULEVARD   SUITE 202    VAN NUYS, CA 91405
Engineer Standley,, Craig Erick; Lic. No.: C87675 6631 MURIETTA AVE      LOS ANGELES, CA 91405

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/6/2020 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 4/15/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 4/15/2020 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 4/28/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/6/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 5/6/2020 Approved FREDDIE RIVERA
Green Building Rough 5/6/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 5/6/2020 Conditional Approval FREDDIE RIVERA
Insulation 5/22/2020 Approved OSVALDO PARAMO
Drywall Nailing 5/28/2020 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 6/2/2020 Approved SABAS ALONSO
Underground Mechanical 6/9/2020 Approved FREDDIE RIVERA
Wood Frame 7/16/2020 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/11/2020 Not Ready for Inspection FREDDIE RIVERA
Final 8/11/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 8/11/2020 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 8/11/2020 Conditional Approval FREDDIE RIVERA
PLUMBING-Final 8/11/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 8/11/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Final 8/28/2020 Approved FREDDIE RIVERA
Final 8/28/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 8/28/2020 Corrections Issued FREDDIE RIVERA
HVAC-Final 8/28/2020 Approved FREDDIE RIVERA
PLUMBING-Final 8/28/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/28/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 8/28/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Not Ready FREDDIE RIVERA
Final 9/21/2020 OK to Issue CofO FREDDIE RIVERA
Green Building Final 9/21/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Approved FREDDIE RIVERA