3305 W 59TH PL 90043
Certificate Information: 3305 W 59TH PL 90043
- Application / Permit
- 20014-20000-01001
- Plan Check / Job No.
- B20VN03839
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 20'-0" X 10'-9" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (615 SQ FT).
- Permit Issued
- Issued on 3/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 3/4/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/11/2020 | JEROME MAGAT PALMA |
| Issued | 3/11/2020 | LADBS |
| CofO in Progress | 9/21/2020 | FREDDIE RIVERA |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
| CofO Issued | 9/27/2020 | DEROLD HAUFF |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/4/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 3/5/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Excel Construction L A Inc; Lic. No.: 998499-B | 7100 VAN NUYS BOULEVARD SUITE 202 VAN NUYS, CA 91405 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/6/2020 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/15/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/15/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 4/28/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/6/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/6/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/6/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/6/2020 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 5/22/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 5/28/2020 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 6/2/2020 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/9/2020 | Approved | FREDDIE RIVERA |
| Wood Frame | 7/16/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 8/11/2020 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 8/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Final | 8/11/2020 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Final | 8/11/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/28/2020 | Approved | FREDDIE RIVERA |
| Final | 8/28/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 8/28/2020 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 8/28/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 8/28/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/28/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 9/21/2020 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 9/21/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/21/2020 | SGSOV Approved | FREDDIE RIVERA |