1175 S MULLEN AVE 90019

Certificate Information: 1175 S MULLEN AVE 90019

Application / Permit
20014-20000-00993
Plan Check / Job No.
B20VN03823
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2 STORY 24' X 25' ACCESSORY DWELLING UNIT ATTACHED TO (E) GARAGE. ALL WORK PER ENGINEER.
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Green Plans Picked Up 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 PINANK PATEL
Corrections Issued 3/23/2020 PINANK PATEL
Quality Review Completed 3/24/2020 ABDUL CHEGENI
Building Plans Picked Up 3/25/2020 APPLICANT
Plan Check Approved 9/2/2020 PINANK PATEL
Issued 9/10/2020 APPLICANT
CofO in Progress 6/13/2022 STUART CHAPMAN
No Progress 7/13/2022 STUART CHAPMAN
CofO in Progress 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/7/2020 RIDWAN HARDY
Green Code Cleared 5/28/2020 AARON COSTA
Address approval Cleared 6/12/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/12/2020 JEANIE LAM
Sewer availability Cleared 6/12/2020 JEANIE LAM
Low Impact Development Cleared 7/14/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/21/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2020 Approved STUART CHAPMAN
METHANE-Barrier 11/4/2020 Approved STUART CHAPMAN
METHANE-Subgrade 11/4/2020 Approved STUART CHAPMAN
Insulation 12/14/2020 Partial Approval STUART CHAPMAN
Wood Frame 12/14/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval STUART CHAPMAN
Green Building Rough 12/17/2020 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Partial Approval STUART CHAPMAN
Green Building Rough 1/5/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 1/5/2021 Approved STUART CHAPMAN
Wood Frame 1/21/2021 Partial Approval STUART CHAPMAN
Special/Order Compliance 2/1/2021 Approved STUART CHAPMAN
Special/Order Compliance 2/19/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/10/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 3/10/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 3/24/2021 Approved STUART CHAPMAN
HVAC-Rough 3/24/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/24/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 3/24/2021 Approved STUART CHAPMAN
Wood Frame 3/24/2021 Partial Approval STUART CHAPMAN
Insulation 5/17/2021 Approved STUART CHAPMAN
Drywall Nailing 6/4/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 6/4/2021 Approved CHRISTOPHER DELLEFIELD
Gas Test 7/6/2021 Approved BENEVA JACKSON
Underground Mechanical 7/6/2021 Approved BENEVA JACKSON
Sewer 8/9/2021 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 8/9/2021 Partial Approval STUART CHAPMAN
Sewer 8/13/2021 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/29/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Final 11/29/2021 Corrections Issued SHAVONNE ESPINOZA
Gas Test 11/29/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Final 11/29/2021 Not Ready for Inspection SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Approved SHAVONNE ESPINOZA
Service/Power Release 11/29/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Smoke Detectors 11/29/2021 Approved SHAVONNE ESPINOZA
Gas Test 1/14/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/27/2022 Approved STUART CHAPMAN
Final 1/27/2022 Corrections Issued STUART CHAPMAN
Green Building Final 1/27/2022 Approved STUART CHAPMAN
Service/Power Release 1/27/2022 Not Ready for Inspection STUART CHAPMAN
Pre-Inspection 3/3/2022 Approved ALEJANDRO DE ARTOLA
Final 4/27/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 6/9/2022 Approved STUART CHAPMAN
Final 6/9/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 6/9/2022 Approved STUART CHAPMAN
PLUMBING-Final 6/9/2022 Approved STUART CHAPMAN
Service/Power Release 6/17/2022 Approved STUART CHAPMAN
Special/Order Compliance 7/13/2022 Corrections Issued STUART CHAPMAN