7365 N HILLSVIEW CT 91307

Certificate Information: 7365 N HILLSVIEW CT 91307

Application / Permit
20014-20000-00990
Plan Check / Job No.
B20VN03812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
192 SF FIRST FLOOR ADDITION TO THE FRONT AND 66 SF FIRST FLOOR ADDITION TO THE SIDE OF (E) 2-STORY SFD
Permit Issued
Issued on 8/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 AMIR DANAI
Corrections Issued 6/16/2020 AMIR DANAI
Quality Review Completed 6/26/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 7/7/2020 APPLICANT
Green Plans Picked Up 7/23/2020 APPLICANT
Plan Check Approved 8/4/2020 AMIR DANAI
Issued 8/13/2020 APPLICANT
CofO in Progress 1/24/2023 CHRIS CHRISTENSEN
Permit Finaled 5/2/2023 JOHN JANSON
CofO Issued 5/2/2023 JOHN JANSON
Permit Finaled 5/2/2023 JOHN JANSON

Permit Application Clearance Information

Hold Cleared 6/9/2020 CYNTHIA RYAN
Eng Process Fee Ord 176,300 Cleared 7/16/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 7/16/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 7/30/2020 DAVID MATSON
GPI Written Notices Cleared 8/4/2020 AMIR DANAI
Grading Pre-Inspection Cleared 8/4/2020 AMIR DANAI

Contact Information

No Data Available.

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Not Ready for Inspection DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 12/22/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 12/22/2021 Corrections Issued DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 12/22/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 2/3/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 2/3/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Corrections Issued STEVEN BACK
Green Building Rough 2/3/2022 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 2/3/2022 Not Ready for Inspection STEVEN BACK
Special/Order Compliance 2/3/2022 Approved STEVEN BACK
ELECTRICAL-Rough 2/16/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 2/16/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 2/24/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/3/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 3/16/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/16/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 3/16/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/16/2022 Corrections Issued CHRIS CHRISTENSEN
Deputy Wood Construction 3/17/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 4/1/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Approved CHRIS CHRISTENSEN
Wood Frame 4/1/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 4/20/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 4/20/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/20/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 7/7/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 11/21/2022 Approved CHRIS CHRISTENSEN
Final 11/21/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/21/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 11/21/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 11/21/2022 Approved CHRIS CHRISTENSEN
Final 1/23/2023 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved CHRIS CHRISTENSEN