1627 N GOWER ST 90028
Certificate Information: 1627 N GOWER ST 90028
- Application / Permit
- 20014-20000-00986
- Plan Check / Job No.
- B20VN03797
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE OF EXISTING RETAIL SALES TO RESTAUARANT ( BANQUET HALL) ADDITION OF MEZZANINE FOR ADDITIONAL SITTING & ACCESSORY STORAGE ROOM
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- CofO Issued on 2/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/16/2020 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 3/17/2020 | STEVEN KIM |
| Building Plans Picked Up | 3/17/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 3/17/2020 | APPLICANT |
| Green Plans Picked Up | 3/17/2020 | APPLICANT |
| Applicant returned to address corrections | 6/3/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/9/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/28/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 8/5/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 8/11/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 8/26/2020 | SALVADOR QUINTANILLA |
| Issued | 9/4/2020 | APPLICANT |
| CofO in Progress | 2/7/2022 | SORIN CIRSTOIU |
| CofO Issued | 2/7/2022 | ERNESTO CORRAL |
| Permit Finaled | 2/7/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Fire Marshall Fire Life Safety | Cleared | 3/25/2020 | ANDREW KO |
| Address approval | Cleared | 4/6/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 4/6/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 4/8/2020 | JOHN CONNEALLY |
| ZA Case | Cleared | 4/15/2020 | RONY GIRON |
| Comm Cor/Mini-Mall | Cleared | 5/5/2020 | ANACANY HURTADO |
| ZI | Cleared | 5/5/2020 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2020 | ABDULLAH SADOZAI |
| Redevelopment Project Area | Cleared | 5/21/2020 | DAVID URITA |
| "D" conditions | Cleared | 5/22/2020 | SARAHI ORTEGA |
| DAS Clearance | Cleared | 5/28/2020 | NORLITO MEDRANO |
| Green Code | Cleared | 5/28/2020 | AARON COSTA |
| Food establishment approval | Cleared | 6/1/2020 | LACDHS APPROVED |
Contact Information
| Contractor | Spacecraft; Lic. No.: 821656-B | 7507 W SUNSET BLVD #12 LOS ANGELES, CA 90046 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/11/2020 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 9/11/2020 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/11/2020 | Partial Approval | EDWIN GREGORYONA |
| Wall Anchors | 9/11/2020 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 9/11/2020 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 11/18/2020 | Approved | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 12/9/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Wood Frame | 12/9/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Wood Frame | 1/5/2021 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 1/13/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 1/13/2021 | Approved | RUSSELL BONVOULOIR |
| Verify Rec and Parks Fee Memo | 1/13/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 10/12/2021 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 10/12/2021 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 10/12/2021 | Partial Inspection | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 10/12/2021 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 10/12/2021 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Not Ready | DAVID BURKHEAD |
| Final | 1/31/2022 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 1/31/2022 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 1/31/2022 | Partial Inspection | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 1/31/2022 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | SORIN CIRSTOIU |
| Final | 2/7/2022 | Conditional Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 2/7/2022 | Approved | SORIN CIRSTOIU |
| Green Building Final | 2/7/2022 | Approved | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 2/7/2022 | Approved | SORIN CIRSTOIU |