1627 N GOWER ST 90028

Certificate Information: 1627 N GOWER ST 90028

Application / Permit
20014-20000-00986
Plan Check / Job No.
B20VN03797
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE OF EXISTING RETAIL SALES TO RESTAUARANT ( BANQUET HALL) ADDITION OF MEZZANINE FOR ADDITIONAL SITTING & ACCESSORY STORAGE ROOM
Permit Issued
Issued on 9/4/2020
Issuing Office
Current Status
CofO Issued on 2/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SALVADOR QUINTANILLA
Corrections Issued 3/16/2020 RUDOLF KINAR MELIKOFF
Quality Review Completed 3/17/2020 STEVEN KIM
Building Plans Picked Up 3/17/2020 APPLICANT
Disabled Access Plans Picked Up 3/17/2020 APPLICANT
Green Plans Picked Up 3/17/2020 APPLICANT
Applicant returned to address corrections 6/3/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 7/9/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 7/28/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 8/5/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 8/11/2020 SALVADOR QUINTANILLA
Plan Check Approved 8/26/2020 SALVADOR QUINTANILLA
Issued 9/4/2020 APPLICANT
CofO in Progress 2/7/2022 SORIN CIRSTOIU
CofO Issued 2/7/2022 ERNESTO CORRAL
Permit Finaled 2/7/2022 ERNESTO CORRAL

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 3/25/2020 ANDREW KO
Address approval Cleared 4/6/2020 JUAN ASHTON
Sewer availability Cleared 4/6/2020 JUAN ASHTON
Hydrant and Access approval Cleared 4/8/2020 JOHN CONNEALLY
ZA Case Cleared 4/15/2020 RONY GIRON
Comm Cor/Mini-Mall Cleared 5/5/2020 ANACANY HURTADO
ZI Cleared 5/5/2020 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 5/15/2020 ABDULLAH SADOZAI
Redevelopment Project Area Cleared 5/21/2020 DAVID URITA
"D" conditions Cleared 5/22/2020 SARAHI ORTEGA
DAS Clearance Cleared 5/28/2020 NORLITO MEDRANO
Green Code Cleared 5/28/2020 AARON COSTA
Food establishment approval Cleared 6/1/2020 LACDHS APPROVED

Contact Information

Contractor Spacecraft; Lic. No.: 821656-B 7507 W SUNSET BLVD #12      LOS ANGELES, CA 90046
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/11/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/11/2020 Partial Approval EDWIN GREGORYONA
Wall Anchors 9/11/2020 Partial Inspection EDWIN GREGORYONA
Wood Frame 9/11/2020 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 11/18/2020 Approved RUSSELL BONVOULOIR
T-Bar Ceiling 12/9/2020 Partial Approval RUSSELL BONVOULOIR
Wood Frame 12/9/2020 Conditional Approval RUSSELL BONVOULOIR
Wood Frame 1/5/2021 Approved RUSSELL BONVOULOIR
Drywall Nailing 1/13/2021 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 1/13/2021 Approved RUSSELL BONVOULOIR
Verify Rec and Parks Fee Memo 1/13/2021 Approved RUSSELL BONVOULOIR
Final 10/12/2021 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 10/12/2021 Partial Inspection SORIN CIRSTOIU
Green Building Final 10/12/2021 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 10/12/2021 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 10/12/2021 Approved SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Not Ready DAVID BURKHEAD
Final 1/31/2022 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 1/31/2022 Partial Inspection SORIN CIRSTOIU
Green Building Final 1/31/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 1/31/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved SORIN CIRSTOIU
Final 2/7/2022 Conditional Approval SORIN CIRSTOIU
Footing/Foundation/Slab 2/7/2022 Approved SORIN CIRSTOIU
Green Building Final 2/7/2022 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 2/7/2022 Approved SORIN CIRSTOIU