5544 N MORELLA AVE 91607

Certificate Information: 5544 N MORELLA AVE 91607

Application / Permit
20014-20000-00964
Plan Check / Job No.
B20VN03688
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2) 7' X 14'-8" ADDITIONS TO DETACHED 2-CAR GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Assigned to Plan Check Engineer 3/9/2020 JENNIFER LEE
Corrections Issued 3/9/2020 JENNIFER LEE
Applicant returned to address corrections 3/16/2020 ALDOUS CHIC
Plan Check Approved 3/27/2020 GURUNATH NESARAJAH
Issued 4/16/2020 LADBS
CofO in Progress 7/1/2021 THOMAS FINNILA
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/9/2020 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 3/9/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/18/2020 ROSE MARIE SMITH
Sewer availability Cleared 3/18/2020 ROSE MARIE SMITH
Miscellaneous Cleared 3/25/2020 OLGA AYALA
Specific Plan Cleared 3/25/2020 OLGA AYALA

Contact Information

Contractor All Construction Services; Lic. No.: 1056091-B 9018 BALBOA BLVD #509      NORTHRIDGE, CA 91325
Engineer Minn,, Wen-Chung; Lic. No.: C42605 3358 W 157TH ST      GARDENA, CA 90249

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/9/2020 Not Ready for Inspection JEFFREY PARD
Underground Mechanical 6/9/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 6/11/2020 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 6/11/2020 Approved BRENDAN LOONEY
Footing/Foundation/Slab 6/16/2020 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/18/2020 Approved THOMAS FINNILA
PLUMBING-Rough 6/18/2020 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/9/2020 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 7/9/2020 Approved THOMAS FINNILA
Green Building Rough 7/9/2020 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 7/9/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/14/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/14/2020 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/14/2020 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 8/25/2020 Approved THOMAS FINNILA
Insulation 8/25/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 8/25/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/25/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/1/2020 Approved THOMAS FINNILA
Green Building Rough 9/1/2020 Approved THOMAS FINNILA
Insulation 9/1/2020 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 9/1/2020 Partial Approval THOMAS FINNILA
MERV13>=Rough 9/1/2020 Approved THOMAS FINNILA
Drywall Nailing 9/10/2020 Approved DANIEL DREW
Shower Pan 9/28/2020 Approved THOMAS FINNILA
Final 11/24/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Final 11/24/2020 Corrections Issued THOMAS FINNILA
MERV13>=Final 11/24/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 11/24/2020 Not Ready for Inspection THOMAS FINNILA
Final 5/18/2021 Partial Inspection THOMAS FINNILA
Green Building Final 5/18/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Final 5/18/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 5/18/2021 Approved THOMAS FINNILA
Final 7/1/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 7/1/2021 Approved THOMAS FINNILA