6911 N ZELZAH AVE 91335

Certificate Information: 6911 N ZELZAH AVE 91335

Application / Permit
20014-20000-00953
Plan Check / Job No.
B20VN03657
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-0" X 20'-0" DETACHED GARAGE AND ADD 5'-6" X 14'-0" FOR (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 6/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 JENNIFER LEE
Corrections Issued 3/5/2020 JENNIFER LEE
Plan Check Approved 3/13/2020 ROSENDO MEDINA
Issued 6/18/2020 LADBS
CofO in Progress 9/14/2021 VINCENT HANLEY
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/5/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/5/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 3/5/2020 GUILLERMO PETRA
Sewer availability Cleared 3/5/2020 GUILLERMO PETRA
Construction near power lines Cleared 3/13/2020 TORI CHEN

Contact Information

Contractor New Generation Home Improvements Inc; Lic. No.: 938552-B 5805 WHITE OAK AVE #18431      ENCINO, CA 91416
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/23/2020 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 10/23/2020 Corrections Issued DAVID SANDOVAL
Sewer 10/23/2020 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/10/2020 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/17/2020 Approved VINCENT HANLEY
Wood Frame 12/24/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 1/8/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/2/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/2/2021 Approved VINCENT HANLEY
Green Building Rough 3/2/2021 Approved VINCENT HANLEY
HVAC-Rough 3/2/2021 Approved VINCENT HANLEY
PLUMBING-Rough 3/2/2021 Approved VINCENT HANLEY
Insulation 3/18/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/18/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 4/19/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/19/2021 Approved VINCENT HANLEY
Shower Pan 4/19/2021 Approved VINCENT HANLEY
Final 8/26/2021 Corrections Issued STEVEN BACK
Green Building Final 8/26/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/26/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 8/26/2021 Approved STEVEN BACK
ELECTRICAL-Final 9/14/2021 Approved VINCENT HANLEY
Final 9/14/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 9/14/2021 Approved VINCENT HANLEY
HVAC-Final 9/14/2021 Approved VINCENT HANLEY
PLUMBING-Final 9/14/2021 Approved VINCENT HANLEY