22133 W RUNNYMEDE ST 91303

Certificate Information: 22133 W RUNNYMEDE ST 91303

Application / Permit
20014-20000-00934
Plan Check / Job No.
B20VN03608
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BATHRM ADDITION (8'x16'8") TO EX 1-STORY SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Assigned to Plan Check Engineer 3/2/2020 HAYATO TSUCHIYA
Plan Check Approved 3/2/2020 HAYATO TSUCHIYA
Issued 3/4/2020 LADBS
CofO in Progress 12/21/2020 DAVID STEPANYAN
Permit Finaled 12/23/2020 JOHN JANSON
CofO Issued 12/23/2020 JOHN JANSON
Permit Finaled 12/23/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/28/2020 JOHN LIN
Roof/Waste drainage to street Cleared 2/28/2020 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/2/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 6/3/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 6/9/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 7/13/2020 Approved DAVID STEPANYAN
Gas Test 7/13/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 7/13/2020 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 7/20/2020 Approved DAVID STEPANYAN
Green Building Rough 7/20/2020 Approved DAVID STEPANYAN
HVAC-Rough 7/20/2020 Approved DAVID STEPANYAN
PLUMBING-Rough 7/20/2020 Approved DAVID STEPANYAN
Insulation 7/22/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 7/22/2020 Partial Approval DAVID STEPANYAN
Drywall Nailing 7/28/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 7/28/2020 Approved DAVID STEPANYAN
Final 11/17/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 11/17/2020 Approved DAVID STEPANYAN
Smoke Detectors 11/17/2020 Corrections Issued DAVID STEPANYAN
Special/Order Compliance 11/17/2020 Partial Approval DAVID STEPANYAN
Final 12/21/2020 OK to Issue CofO DAVID STEPANYAN
Smoke Detectors 12/21/2020 Approved DAVID STEPANYAN