225 N HOMEWOOD ROAD 90049

Certificate Information: 225 N HOMEWOOD ROAD 90049

Application / Permit
20014-20000-00932
Plan Check / Job No.
B20VN03595
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 19'-4" X 19'-9" SECOND FLOOR ADDITION TO (E) 2-STORY SFD AND REMODEL PORTION OF SECOND STORY, NEW SKYLIGHTS IN (E) PATIO COVER. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/21/2020
Issuing Office
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 JENNIFER LEE
Corrections Issued 3/26/2020 JENNIFER LEE
Quality Review Completed 3/26/2020 STEVEN KIM
Building Plans Picked Up 4/6/2020 APPLICANT
Green Plans Picked Up 4/6/2020 APPLICANT
Plan Check Approved 6/3/2020 JENNIFER LEE
Issued 8/21/2020 APPLICANT
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/8/2020 EMIL KYUPELYAN
Sewer availability Cleared 4/8/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 4/22/2020 PAMELA TENEZA
Green Code Cleared 5/22/2020 MICHAEL AYERS
Grading Pre-Inspection Cleared 6/3/2020 JENNIFER LEE

Contact Information

Contractor Foster D A Construction; Lic. No.: 673613-B P O BOX 1699      THOUSAND OAKS, CA 91358
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 10/5/2020 Not Ready for Inspection TIM CHRISTENSEN
Footing/Foundation/Slab 10/13/2020 Approved TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Partial Approval TIM CHRISTENSEN
PLUMBING-Rough 10/28/2020 Partial Approval TIM CHRISTENSEN
Wood Frame 10/28/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval PIERRE VEGA
PLUMBING-Rough 11/18/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/24/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 12/4/2020 Approved EVAN COOPER
Shower Pan 12/4/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 12/15/2020 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 12/15/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 12/18/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 12/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Steel/Welding 12/23/2020 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/11/2021 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 1/11/2021 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 1/13/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 1/15/2021 Approved CHRISTOPHER WILSON
HVAC-Rough 1/20/2021 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 1/27/2021 Corrections Issued EVAN COOPER
Green Building Rough 1/27/2021 Not Ready for Inspection EVAN COOPER
Insulation 2/1/2021 Conditional Approval JUAN VALENZUELA
Drywall Nailing 2/5/2021 Approved JUAN VALENZUELA
Green Building Rough 2/5/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/10/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 12/8/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/8/2023 Approved KEVIN SARGSYAN
Final 12/8/2023 Corrections Issued KEVIN SARGSYAN
Green Building Final 12/8/2023 Approved KEVIN SARGSYAN
HVAC-Final 12/8/2023 Approved KEVIN SARGSYAN
PLUMBING-Final 12/8/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 12/8/2023 Approved KEVIN SARGSYAN
Final 12/13/2023 Conditional Approval KEVIN SARGSYAN