2475 S COLBY AVE 90064

Certificate Information: 2475 S COLBY AVE 90064

Application / Permit
20014-20000-00927
Plan Check / Job No.
B20VN03578
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD & EXPAND (33'-4 1/2"x 18'-10") IRR SHAPE DINING & LIVING RM AND INT. REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 TROY DEGUZMAN
Corrections Issued 4/7/2020 TROY DEGUZMAN
Quality Review Completed 4/7/2020 CHON CHIO KUO
Building Plans Picked Up 5/5/2020 APPLICANT
Green Plans Picked Up 7/10/2020 APPLICANT
Plan Check Approved 10/22/2020 TROY DEGUZMAN
Issued 11/4/2020 APPLICANT
CofO in Progress 5/14/2025 KIRK SANDERS
Permit Finaled 5/15/2025 RICHARD STEINBACH
CofO Issued 5/15/2025 RICHARD STEINBACH
Permit Finaled 5/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Green Code Cleared 7/17/2020 AARON COSTA
Hydrant and Access approval Cleared 9/2/2020 MATTHEW CRAIG
Sewer availability Cleared 9/18/2020 DINAH GARIN
Specific Plan Cleared 9/21/2020 MIGUEL GAMBOA
Specific Plan Cleared 9/21/2020 MIGUEL GAMBOA
ZI Cleared 9/21/2020 MIGUEL GAMBOA
ZI Cleared 9/21/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 9/22/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 9/22/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Keshishian,, Vahram; Lic. No.: S6482 1102 SAN RAFAEL AVE      GLENDALE, CA 91202

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2021 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 6/15/2021 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/18/2021 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/18/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/6/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 7/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
MERV13>=Rough 7/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 7/6/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 1/11/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/8/2022 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 6/8/2022 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval KENNETH NAGLE
HVAC-Rough 6/8/2022 Approved KENNETH NAGLE
MERV13>=Rough 6/8/2022 Approved KENNETH NAGLE
BUILDING-Rough-Frame 6/14/2022 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved STEPHANIE SWANSON
Green Building Rough 6/14/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 6/14/2022 Partial Approval STEPHANIE SWANSON
Green Building Rough 6/17/2022 Approved JOHNNY MIRANDA
Insulation 6/17/2022 Approved JOHNNY MIRANDA
Drywall Nailing 6/28/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/6/2022 Approved KENNETH NAGLE
Sewer 7/6/2022 Approved KENNETH NAGLE
ELECTRICAL-Final 11/7/2022 Corrections Issued ASHLEY THOMPSON
Service/Power Release 11/7/2022 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 11/8/2022 Approved ASHLEY THOMPSON
Service/Power Release 11/8/2022 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 11/9/2022 Approved ASHLEY THOMPSON
HVAC-Final 11/14/2022 Approved ASHLEY THOMPSON
PLUMBING-Final 11/14/2022 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 11/16/2022 Approved OGANES TARAKHCHYAN
Gas Test 11/16/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 11/16/2022 Approved OGANES TARAKHCHYAN
Final 12/19/2022 Corrections Issued OGANES TARAKHCHYAN
Final 12/19/2022 Off-Hour Fees Due
Green Building Final 12/19/2022 Approved OGANES TARAKHCHYAN
Green Building Final 12/19/2022 Off-Hour Fees Due
MERV13>=Final 12/19/2022 Approved OGANES TARAKHCHYAN
MERV13>=Final 12/19/2022 Off-Hour Fees Due
PLUMBING-Final 12/19/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/19/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 12/19/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 12/19/2022 Approved OGANES TARAKHCHYAN
Smoke Detectors 12/19/2022 Off-Hour Fees Due
Final 5/13/2025 OK to Issue CofO KIRK SANDERS