3560 S REDWOOD AVE 90066

Certificate Information: 3560 S REDWOOD AVE 90066

Application / Permit
20014-20000-00911
Plan Check / Job No.
B20VN03514
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (54'-3 1/2"x 28'-0") 2ND STORY AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 7/27/2020
Issuing Office
Current Status
CofO Issued on 5/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Green Plans Picked Up 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 TROY DEGUZMAN
Corrections Issued 3/22/2020 TROY DEGUZMAN
Quality Review Completed 3/23/2020 CHON CHIO KUO
Building Plans Picked Up 3/23/2020 APPLICANT
Applicant returned to address corrections 6/5/2020 TROY DEGUZMAN
Plan Check Approved 6/5/2020 TROY DEGUZMAN
Issued 7/27/2020 APPLICANT
CofO in Progress 5/4/2021 ENRIQUE MIRELES
CofO Issued 5/6/2021 VINCENT COTTON
Permit Finaled 5/6/2021 VINCENT COTTON

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/24/2020 GEORGE SUCHAND
Low Impact Development Cleared 5/1/2020 MARTIN FRAGOSO
Green Code Cleared 5/6/2020 AARON COSTA
Roof/Waste drainage to street Cleared 5/8/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/12/2020 DINAH GARIN
Sewer availability Cleared 5/12/2020 DINAH GARIN

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 14263 VALLEY VISTA BLVD.      SHERMAN OAKS, CA 91403
Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/14/2020 Approved CRAIG DAVIS
Footing/Foundation/Slab 8/14/2020 Approved CRAIG DAVIS
Underground Mechanical 8/24/2020 Not Ready for Inspection MATT KELLERMAN
Underground Mechanical 8/26/2020 Partial Approval CRAIG DAVIS
Deputy Wood Construction 8/28/2020 No Access for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 9/11/2020 Partial Approval JOHNNY MIRANDA
Structural Steel Frame 9/11/2020 Not Ready for Inspection JOHNNY MIRANDA
Deputy Wood Construction 9/14/2020 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 9/15/2020 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 9/18/2020 Conditional Approval JOHNNY MIRANDA
PLUMBING-Rough 10/16/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Corrections Issued JOHNNY MIRANDA
Gas Test 10/21/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 11/4/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval ENRIQUE MIRELES
HVAC-Rough 11/4/2020 Approved ENRIQUE MIRELES
Underground Mechanical 11/4/2020 Partial Approval ENRIQUE MIRELES
BUILDING-Rough-Frame 11/12/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Approved ENRIQUE MIRELES
Green Building Rough 11/12/2020 Approved ENRIQUE MIRELES
Shower Pan 11/12/2020 Approved ENRIQUE MIRELES
Wood Frame 11/12/2020 Approved ENRIQUE MIRELES
Insulation 11/17/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/18/2020 Partial Approval ENRIQUE MIRELES
Interior/Exterior Lathing 11/19/2020 Approved ENRIQUE MIRELES
Drywall Nailing 11/23/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/23/2020 Approved ENRIQUE MIRELES
Gas Test 12/3/2020 No Access for Inspection ENRIQUE MIRELES
Gas Test 12/4/2020 Approved ENRIQUE MIRELES
HVAC-Final 2/8/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 2/8/2021 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 2/8/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 2/11/2021 Approved ENRIQUE MIRELES
HVAC-Final 2/11/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 2/11/2021 Approved ENRIQUE MIRELES
Service/Power Release 2/11/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 2/12/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 2/12/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 2/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 2/12/2021 Approved ENRIQUE MIRELES
Final 5/4/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 5/4/2021 Approved ENRIQUE MIRELES