3560 S REDWOOD AVE 90066
Certificate Information: 3560 S REDWOOD AVE 90066
- Application / Permit
- 20014-20000-00911
- Plan Check / Job No.
- B20VN03514
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (54'-3 1/2"x 28'-0") 2ND STORY AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/27/2020
- Issuing Office
- Current Status
- CofO Issued on 5/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Green Plans Picked Up | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/22/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/23/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/23/2020 | APPLICANT |
| Applicant returned to address corrections | 6/5/2020 | TROY DEGUZMAN |
| Plan Check Approved | 6/5/2020 | TROY DEGUZMAN |
| Issued | 7/27/2020 | APPLICANT |
| CofO in Progress | 5/4/2021 | ENRIQUE MIRELES |
| CofO Issued | 5/6/2021 | VINCENT COTTON |
| Permit Finaled | 5/6/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/24/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 5/1/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 5/6/2020 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 5/8/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | DINAH GARIN |
| Sewer availability | Cleared | 5/12/2020 | DINAH GARIN |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 14263 VALLEY VISTA BLVD. SHERMAN OAKS, CA 91403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2020 | Approved | CRAIG DAVIS |
| Footing/Foundation/Slab | 8/14/2020 | Approved | CRAIG DAVIS |
| Underground Mechanical | 8/24/2020 | Not Ready for Inspection | MATT KELLERMAN |
| Underground Mechanical | 8/26/2020 | Partial Approval | CRAIG DAVIS |
| Deputy Wood Construction | 8/28/2020 | No Access for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Partial Approval | JOHNNY MIRANDA |
| Structural Steel Frame | 9/11/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Deputy Wood Construction | 9/14/2020 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Steel/Welding | 9/15/2020 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Steel/Welding | 9/18/2020 | Conditional Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/16/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Corrections Issued | JOHNNY MIRANDA |
| Gas Test | 10/21/2020 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/4/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2020 | Partial Approval | ENRIQUE MIRELES |
| HVAC-Rough | 11/4/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 11/4/2020 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Shower Pan | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 11/17/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/18/2020 | Partial Approval | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/19/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/23/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/23/2020 | Approved | ENRIQUE MIRELES |
| Gas Test | 12/3/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Gas Test | 12/4/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/8/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 2/8/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 2/8/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/11/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/11/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/11/2021 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/11/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 2/12/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/12/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/12/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 2/12/2021 | Approved | ENRIQUE MIRELES |
| Final | 5/4/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 5/4/2021 | Approved | ENRIQUE MIRELES |