8070 W LAURELMONT DR 90046

Certificate Information: 8070 W LAURELMONT DR 90046

Application / Permit
20014-20000-00910
Plan Check / Job No.
B20VN03508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY WITH NEW GARAGE ADDITION TO (E) TWO STORY SFD, CONVERT (E) 400SF GARAGE TO DEN AND MAJOR REMODEL_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D. "COMPLY WITH DEPARTMENT ORDER effective date 09/14/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 DAWN MC NULTY
Corrections Issued 4/2/2020 DAWN MC NULTY
Quality Review Completed 4/3/2020 CHON CHIO KUO
Building Plans Picked Up 4/14/2020 APPLICANT
Green Plans Picked Up 5/29/2020 APPLICANT
Applicant returned to address corrections 11/9/2020 DAWN MC NULTY
Applicant returned to address corrections 11/10/2020 DAWN MC NULTY
Applicant returned to address corrections 1/27/2022 DAWN MC NULTY
Applicant returned to address corrections 7/1/2022 DAWN MC NULTY
Applicant returned to address corrections 7/11/2022 DAWN MC NULTY
Plan Check Approved 7/27/2022 DAWN MC NULTY
Issued 7/27/2022 APPLICANT
CofO in Progress 8/21/2024 STUART CHAPMAN
Permit Finaled 9/3/2024 RONALD MYRICK
CofO Issued 9/3/2024 RONALD MYRICK
Permit Finaled 9/3/2024 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/28/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 7/28/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 7/28/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/28/2020 CELINA MORENO
Permit Cleared 7/28/2020 CELINA MORENO
Sewer availability Cleared 7/28/2020 CELINA MORENO
CPC Cleared 8/7/2020 HERMINIGILDO AGUSTIN
CPC Cleared 8/7/2020 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 8/19/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/21/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/28/2020 WALLIE JONG
GPI Written Notices Cleared 11/10/2020 DAWN MC NULTY
Grading Pre-Inspection Cleared 11/10/2020 DAWN MC NULTY
Address approval Cleared 2/3/2022 CHRISTOPHER ROCHA
Miscellaneous Cleared 7/25/2022 DAWN MC NULTY
Miscellaneous Cleared 7/25/2022 DAWN MC NULTY

Contact Information

Architect Lopez,, Craig Joseph; Lic. No.: C14263 155 GRANADA ST STE "L"      CAMARILLO, CA 93010
Contractor Owner-Builder       ,
Engineer Michal,, Jerry Lee; Lic. No.: GE2515 2499 ROCK VIEW GLEN      ESCONDIDO, CA 92026

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/15/2022 Conditional Approval RAUL BARAJAS
Deputy Grading 9/19/2022 Conditional Approval RAUL BARAJAS
Deputy Grading 9/21/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/28/2022 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 9/28/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 9/28/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 9/28/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/30/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 10/13/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 10/14/2022 Not Ready for Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 10/14/2022 Corrections Issued BRIAN SULLIVAN
Piling/Pier/Caisson 10/17/2022 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 10/19/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 10/26/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 10/27/2022 Partial Approval BRIAN SULLIVAN
Piling/Pier/Caisson 10/27/2022 Partial Approval BRIAN SULLIVAN
Deputy Steel/Welding 11/1/2022 Conditional Approval RAUL BARAJAS
Deputy Grading 11/15/2022 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 11/21/2022 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 11/22/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/30/2022 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 12/22/2022 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 12/30/2022 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 12/30/2022 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 12/30/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 1/13/2023 Partial Approval JOAQUIN GREENOUGH
Piling/Pier/Caisson 1/13/2023 Partial Approval JOAQUIN GREENOUGH
Deputy Grading 1/24/2023 Approved STUART CHAPMAN
Deputy Steel/Welding 1/25/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 2/9/2023 Conditional Approval STUART CHAPMAN
Deputy Reinf. Concrete 2/22/2023 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/30/2023 Partial Approval STUART CHAPMAN
Piling/Pier/Caisson 3/30/2023 Partial Approval STUART CHAPMAN
Deputy Reinf. Concrete 3/31/2023 Conditional Approval STUART CHAPMAN
Deputy Drilled-In Anchors 4/11/2023 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 4/17/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 4/17/2023 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/17/2023 Approved STUART CHAPMAN
Wood Frame 4/17/2023 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 4/25/2023 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 4/25/2023 Conditional Approval STUART CHAPMAN
Green Building Rough 4/25/2023 Approved STUART CHAPMAN
HVAC-Rough 4/25/2023 Approved STUART CHAPMAN
Insulation 4/25/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/25/2023 Partial Approval STUART CHAPMAN
Shower Pan 4/25/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 4/25/2023 Approved STUART CHAPMAN
Deputy Steel/Welding 5/1/2023 Conditional Approval STUART CHAPMAN
Drywall Nailing 5/1/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/3/2023 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/5/2023 Not Ready for Inspection STUART CHAPMAN
Deputy Drilled-In Anchors 6/9/2023 Conditional Approval STUART CHAPMAN
Deputy Reinf. Concrete 6/9/2023 Conditional Approval STUART CHAPMAN
Deputy Drilled-In Anchors 6/16/2023 Conditional Approval STUART CHAPMAN
Deputy Steel/Welding 6/16/2023 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 6/16/2023 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 7/18/2023 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 7/18/2023 Partial Approval RAUL BARAJAS
Insulation 7/19/2023 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 10/5/2023 Approved STUART CHAPMAN
Final 10/5/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/5/2023 Approved STUART CHAPMAN
Green Building Final 10/5/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/5/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 8/21/2024 Approved STUART CHAPMAN
Final 8/21/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/21/2024 Approved STUART CHAPMAN
PLUMBING-Final 8/21/2024 Approved STUART CHAPMAN