9560 N HILLHAVEN AVE 91042
Certificate Information: 9560 N HILLHAVEN AVE 91042
- Application / Permit
- 20014-20000-00906
- Plan Check / Job No.
- B20VN03499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 10'2-1/2' X 45'1" BATHRM & STORAGE RM ADDN (ACCESSIBLE FROM GARAGE) TO EX 1-STORY SFD W/ ATT GARAGE PER ENGR DESIGN. SEE COMMENTS.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 3/3/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/1/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 3/14/2021 | HAYATO TSUCHIYA |
| Issued | 3/25/2021 | APPLICANT |
| Building Plans Picked Up | 4/7/2021 | APPLICANT |
| CofO in Progress | 4/26/2022 | MATTHEW NELSON |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/15/2020 | PEGGY MALONE-BROWN |
| Low Impact Development | Cleared | 8/17/2020 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 8/18/2020 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/19/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/10/2021 | Approved | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 6/11/2021 | No Access for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/14/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/14/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/6/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/6/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/8/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 9/8/2021 | Approved | WILLIAM KUEHN |
| Gas Test | 9/8/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 9/8/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/15/2021 | Partial Inspection | WILLIAM KUEHN |
| Insulation | 9/30/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Insulation | 10/5/2021 | Approved | WILLIAM KUEHN |
| Deputy Wood Construction | 10/8/2021 | Conditional Approval | WILLIAM KUEHN |
| Drywall Nailing | 10/13/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 10/13/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/8/2021 | Approved | WILLIAM KUEHN |
| Shower Pan | 11/8/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 4/26/2022 | Approved | MATTHEW NELSON |
| Final | 4/26/2022 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 4/26/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 4/26/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/26/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 4/26/2022 | Approved | MATTHEW NELSON |