19560 W LANARK ST 91335
Certificate Information: 19560 W LANARK ST 91335
- Application / Permit
- 20014-20000-00905
- Plan Check / Job No.
- B20VN03479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove (e) patio cover. Add 12'-10" x 5' to relocate front entry. 17' x 4'-5" addition and interior remodel to add two bthrms and relocate the kitchen and bdrm. Reframe portion of (e) roof over family room and kitchen.
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/6/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | ANGELICA DAVE |
| Corrections Issued | 2/27/2020 | ANGELICA DAVE |
| Plan Check Approved | 3/5/2020 | ANGELICA MARTINEZ |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 11/3/2020 | VINCENT HANLEY |
| CofO Issued | 11/6/2020 | DONALD SUNSERI |
| Permit Finaled | 11/6/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 3/3/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/3/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2020 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/25/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2020 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 4/30/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/30/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/26/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/26/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/26/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/26/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/26/2020 | Approved | VINCENT HANLEY |
| Insulation | 5/29/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/29/2020 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 6/4/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/4/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 10/23/2020 | Corrections Issued | HENRY KIM |
| Final | 10/23/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 10/23/2020 | Approved | HENRY KIM |
| HVAC-Final | 10/23/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 10/23/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 10/23/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 11/2/2020 | Approved | VINCENT HANLEY |
| Final | 11/2/2020 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 11/2/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/2/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Approved | VINCENT HANLEY |