14048 W CHAMBERLAIN ST 91340

Certificate Information: 14048 W CHAMBERLAIN ST 91340

Application / Permit
20014-20000-00895
Plan Check / Job No.
B20VN03466
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodeling to remove 15' x 14' from the rear of dwelling, convert 3'5" x 10' to porch, reframe entire roof, add irregular shape 30' x 35' and reconfigure interior per WFPP
Permit Issued
Issued on 3/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/3/2020 JENNIFER LEE
Corrections Issued 3/3/2020 JENNIFER LEE
Applicant returned to address corrections 3/16/2020 ALDOUS CHIC
Plan Check Approved 3/17/2020 HAYATO TSUCHIYA
Issued 3/17/2020 LADBS
CofO in Progress 5/11/2021 JENNIFER RABUCHIN
CofO Issued 11/6/2021 MICHAEL SMITH
Permit Finaled 11/6/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/10/2020 JOHN LIN
Sewer availability Cleared 3/10/2020 JOHN LIN
Low Impact Development Cleared 3/13/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/16/2020 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/13/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 4/21/2020 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/21/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/5/2020 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/5/2020 Approved JENNIFER RABUCHIN
Insulation 5/7/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval JENNIFER RABUCHIN
Wood Frame 6/9/2020 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/16/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/16/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Approved JENNIFER RABUCHIN
Gas Test 6/16/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 6/16/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 6/16/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/16/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/23/2020 Partial Approval JENNIFER RABUCHIN
Shower Pan 6/23/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/6/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 7/21/2020 Conditional Approval JENNIFER RABUCHIN
Drywall Nailing 7/28/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/23/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 12/23/2020 Corrections Issued JENNIFER RABUCHIN
Final 12/23/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/23/2020 Approved JENNIFER RABUCHIN
Green Building Final 12/23/2020 Approved JENNIFER RABUCHIN
HVAC-Final 12/23/2020 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 12/23/2020 Approved JENNIFER RABUCHIN
METHANE-Final 12/23/2020 Approved JENNIFER RABUCHIN
METHANE-Rough 12/23/2020 Approved JENNIFER RABUCHIN
METHANE-Subgrade 12/23/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 12/23/2020 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 12/23/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/22/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/22/2021 Approved JENNIFER RABUCHIN
Final 2/22/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 2/22/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/22/2021 Approved JENNIFER RABUCHIN
Final 5/11/2021 OK to Issue CofO JENNIFER RABUCHIN
Special/Order Compliance 7/1/2021 Approved JENNIFER RABUCHIN