18315 W INGOMAR ST 91335
Certificate Information: 18315 W INGOMAR ST 91335
- Application / Permit
- 20014-20000-00888
- Plan Check / Job No.
- B20VN03458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED (20'-9" X 25'-2") ADDITION FOR (N) ACCESSORY DWELLING UNIT ATTACHED TO (E) STORAGE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | RAPHAEL ROSAS |
| Corrections Issued | 3/1/2020 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/3/2020 | APPLICANT |
| Applicant returned to address corrections | 3/10/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 3/16/2020 | RAPHAEL ROSAS |
| Issued | 3/18/2020 | LADBS |
| CofO in Progress | 7/29/2021 | DAVID STEPANYAN |
| Permit Finaled | 7/29/2021 | JOHN JANSON |
| CofO Issued | 7/29/2021 | JOHN JANSON |
| Permit Finaled | 7/29/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/3/2020 | JOHN TRIANTAFYLLOS |
| ZA Case | Cleared | 3/3/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 3/3/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 3/3/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 3/3/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 3/3/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 3/3/2020 | PABLO ESTRADA |
| Low Impact Development | Cleared | 3/9/2020 | JORGE MEJIA LEMUS |
| Tract Map conditions | Cleared | 3/9/2020 | PABLO ESTRADA |
| ZI | Cleared | 3/9/2020 | PABLO ESTRADA |
| "T" removal | Cleared | 3/12/2020 | PABLO ESTRADA |
| Tract Map conditions | Cleared | 3/12/2020 | PABLO ESTRADA |
| Roof/Waste drainage to street | Cleared | 3/18/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 2/2/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/2/2021 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 2/4/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/4/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/4/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/19/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Approved | VINCENT HANLEY |
| Gas Test | 2/19/2021 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/19/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/26/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/26/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/26/2021 | Approved | VINCENT HANLEY |
| Insulation | 2/26/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/3/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/3/2021 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/17/2021 | Approved | VINCENT HANLEY |
| Final | 4/1/2021 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/1/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 4/1/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/1/2021 | Approved | VINCENT HANLEY |
| Final | 4/21/2021 | Corrections Issued | SEAN WIRCH |
| Final | 4/29/2021 | Corrections Issued | MICHAEL PELHAM |
| Final | 7/20/2021 | OK to Issue CofO | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | DAVID STEPANYAN |