18315 W INGOMAR ST 91335

Certificate Information: 18315 W INGOMAR ST 91335

Application / Permit
20014-20000-00888
Plan Check / Job No.
B20VN03458
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED (20'-9" X 25'-2") ADDITION FOR (N) ACCESSORY DWELLING UNIT ATTACHED TO (E) STORAGE. ALL WORK PER WFPP.
Permit Issued
Issued on 3/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 2/28/2020 RAPHAEL ROSAS
Corrections Issued 3/1/2020 RAPHAEL ROSAS
Building Plans Picked Up 3/3/2020 APPLICANT
Applicant returned to address corrections 3/10/2020 RAPHAEL ROSAS
Plan Check Approved 3/16/2020 RAPHAEL ROSAS
Issued 3/18/2020 LADBS
CofO in Progress 7/29/2021 DAVID STEPANYAN
Permit Finaled 7/29/2021 JOHN JANSON
CofO Issued 7/29/2021 JOHN JANSON
Permit Finaled 7/29/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/3/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/3/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/3/2020 JOHN TRIANTAFYLLOS
ZA Case Cleared 3/3/2020 PABLO ESTRADA
ZA Case Cleared 3/3/2020 PABLO ESTRADA
ZA Case Cleared 3/3/2020 PABLO ESTRADA
ZA Case Cleared 3/3/2020 PABLO ESTRADA
ZA Case Cleared 3/3/2020 PABLO ESTRADA
ZA Case Cleared 3/3/2020 PABLO ESTRADA
Low Impact Development Cleared 3/9/2020 JORGE MEJIA LEMUS
Tract Map conditions Cleared 3/9/2020 PABLO ESTRADA
ZI Cleared 3/9/2020 PABLO ESTRADA
"T" removal Cleared 3/12/2020 PABLO ESTRADA
Tract Map conditions Cleared 3/12/2020 PABLO ESTRADA
Roof/Waste drainage to street Cleared 3/18/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/2/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/2/2021 Partial Approval VINCENT HANLEY
Sewer 2/2/2021 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 2/4/2021 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/4/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/4/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 2/19/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Approved VINCENT HANLEY
Gas Test 2/19/2021 Partial Approval VINCENT HANLEY
PLUMBING-Rough 2/19/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/26/2021 Approved VINCENT HANLEY
Green Building Rough 2/26/2021 Approved VINCENT HANLEY
HVAC-Rough 2/26/2021 Approved VINCENT HANLEY
Insulation 2/26/2021 Approved VINCENT HANLEY
Drywall Nailing 3/3/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/3/2021 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 3/17/2021 Approved VINCENT HANLEY
Final 4/1/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 4/1/2021 Approved VINCENT HANLEY
Green Building Final 4/1/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/1/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/1/2021 Approved VINCENT HANLEY
Final 4/21/2021 Corrections Issued SEAN WIRCH
Final 4/29/2021 Corrections Issued MICHAEL PELHAM
Final 7/20/2021 OK to Issue CofO DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/20/2021 SGSOV Approved DAVID STEPANYAN