15112 W CALIFA ST 91411
Certificate Information: 15112 W CALIFA ST 91411
- Application / Permit
- 20014-20000-00884
- Plan Check / Job No.
- B20VN03444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 7'-0" X 20'-0" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT. COMPLY WITH DEPARTMENT ORDER effective date 08/13/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/22/2020
- Issuing Office
- Current Status
- CofO Issued on 2/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 3/1/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/27/2020 | APPLICANT |
| Applicant returned to address corrections | 8/12/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/14/2020 | JEROME MAGAT PALMA |
| Issued | 8/22/2020 | APPLICANT |
| CofO in Progress | 1/4/2021 | GORDON ZUBER |
| Permit Finaled | 2/12/2021 | DANIEL SANCHEZ |
| CofO Issued | 2/12/2021 | DANIEL SANCHEZ |
| Permit Finaled | 2/12/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/6/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/11/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 7/29/2020 | RIDWAN HARDY |
| ZI | Cleared | 8/14/2020 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/10/2020 | Approved | GORDON ZUBER |
| Deputy Drilled-In Anchors | 9/14/2020 | Approved | GORDON ZUBER |
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Not Ready for Inspection | GORDON ZUBER |
| Footing/Foundation/Slab | 9/14/2020 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 9/30/2020 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 9/30/2020 | Not Ready for Inspection | GORDON ZUBER |
| Footing/Foundation/Slab | 9/30/2020 | Corrections Issued | GORDON ZUBER |
| Green Building Rough | 9/30/2020 | Not Ready for Inspection | GORDON ZUBER |
| METHANE-Rough | 9/30/2020 | Not Ready for Inspection | GORDON ZUBER |
| Underground Mechanical | 9/30/2020 | Approved | GORDON ZUBER |
| Deputy Drilled-In Anchors | 10/6/2020 | No Result Entered | TIMOTHY KEY |
| Footing/Foundation/Slab | 10/8/2020 | Approved | GORDON ZUBER |
| METHANE-Barrier | 10/8/2020 | Approved | GORDON ZUBER |
| METHANE-Subgrade | 10/8/2020 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 10/16/2020 | Approved | GORDON ZUBER |
| ELECTRICAL-Rough | 10/16/2020 | Approved | GORDON ZUBER |
| Green Building Rough | 10/16/2020 | Approved | GORDON ZUBER |
| METHANE-Rough | 10/16/2020 | Approved | GORDON ZUBER |
| Interior/Exterior Lathing | 10/26/2020 | Approved | GORDON ZUBER |
| Drywall Nailing | 10/30/2020 | Approved | GORDON ZUBER |
| Final | 11/19/2020 | Not Ready for Inspection | GORDON ZUBER |
| Green Building Final | 11/19/2020 | Not Ready for Inspection | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 11/19/2020 | SGSOV Not Ready | GORDON ZUBER |
| Smoke Detectors | 11/19/2020 | Approved | GORDON ZUBER |
| Final | 1/4/2021 | OK to Issue CofO | GORDON ZUBER |
| Green Building Final | 1/4/2021 | Approved | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV Approved | GORDON ZUBER |