7750-7752 W LE BERTHON ST 91042

Certificate Information: 7750-7752 W LE BERTHON ST 91042

Application / Permit
20014-20000-00875
Plan Check / Job No.
B20VN03400
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) FRONT 16'-5" X 9'-11" PATIO COVER TO (N) 9'-11" X 12'-3" TRELLIS, ADD IRREGULAR 23'-5" X 44'-4" SECOND FLOOR ACCESSORY DWELLING UNIT WITH EXTERIOR STAIRS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/19/2020
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2020 APPLICANT
Green Plans Picked Up 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 JENNIFER LEE
Corrections Issued 4/3/2020 JENNIFER LEE
Quality Review Completed 4/7/2020 STEVEN KIM
Building Plans Picked Up 4/8/2020 APPLICANT
Applicant returned to address corrections 8/3/2020 JENNIFER LEE
Plan Check Approved 8/13/2020 JENNIFER LEE
Issued 8/19/2020 APPLICANT
CofO in Progress 1/27/2023 WILLIAM WREN
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/22/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/23/2020 LEE GUILBEAUX
Sewer availability Cleared 4/23/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/23/2020 LEE GUILBEAUX
Green Code Cleared 4/24/2020 AARON COSTA
Grading Pre-Inspection Cleared 5/1/2020 TIMOTHY POWELL
Construction near power lines Cleared 5/6/2020 RIDWAN HARDY
GPI Written Notices Cleared 7/8/2020 JENNIFER LEE
Low Impact Development Cleared 7/9/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 7/14/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/16/2022 Conditional Approval MATTHEW NELSON
Footing/Foundation/Slab 6/28/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/5/2022 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 8/5/2022 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 8/25/2022 Corrections Issued MATTHEW NELSON
Pre-Inspection 8/29/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/1/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 9/1/2022 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 9/19/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 9/19/2022 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 9/26/2022 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 9/26/2022 Approved MATTHEW NELSON
Green Building Rough 9/26/2022 Approved MATTHEW NELSON
HVAC-Rough 9/26/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 9/26/2022 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 9/30/2022 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/6/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/19/2022 Partial Approval MATTHEW NELSON
Shower Pan 10/19/2022 Approved MATTHEW NELSON
Insulation 10/24/2022 Approved MATTHEW NELSON
Drywall Nailing 10/31/2022 Approved MATTHEW NELSON
Final 1/20/2023 Corrections Issued WILLIAM WREN
Green Building Final 1/20/2023 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved WILLIAM WREN
Smoke Detectors 1/20/2023 Approved WILLIAM WREN
Final 1/25/2023 OK to Issue CofO WILLIAM WREN
Green Building Final 1/25/2023 Approved WILLIAM WREN