128 S ALTA VISTA BLVD 90036

Certificate Information: 128 S ALTA VISTA BLVD 90036

Application / Permit
20014-20000-00861
Plan Check / Job No.
B20VN03325
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (13'-2" X 31'-9") ADDITION OF A KITCHEN, FAMILY ROOM, MUD ROOM AND POWDER ROOM TO THE REAR OF THE (E) SFD.
Permit Issued
Issued on 5/28/2020
Issuing Office
Current Status
CofO Issued on 10/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2020 APPLICANT
Assigned to Plan Check Engineer 2/26/2020 JEROME MAGAT PALMA
Corrections Issued 2/26/2020 JEROME MAGAT PALMA
Plan Check Approved 3/12/2020 RAPHAEL ROSAS
Issued 5/28/2020 APPLICANT
CofO in Progress 10/25/2020 CHRIS CHRISTENSEN
Permit Finaled 10/26/2020 DEROLD HAUFF
CofO Issued 10/26/2020 DEROLD HAUFF
Permit Finaled 10/26/2020 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 2/26/2020 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/26/2020 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 2/26/2020 DANG NGUYEN
Miscellaneous Cleared 2/26/2020 DANG NGUYEN
Miscellaneous Cleared 2/26/2020 DANG NGUYEN
Roof/Waste drainage to street Cleared 2/26/2020 APEKSHYA BAJRACHARYA
HPOZ Cleared 2/28/2020 DANIEL MATA
ZI Cleared 2/28/2020 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 1836 PARNELL AVE 202      LOS ANGELES, CA 90025

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 6/18/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 6/18/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/26/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/26/2020 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 6/26/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/26/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/5/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 8/5/2020 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 8/7/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 8/7/2020 Approved ARTHUR SARGSYAN
Green Building Rough 8/7/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/7/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 8/17/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/17/2020 Partial Approval SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Not Ready CHRIS CHRISTENSEN
ELECTRICAL-Final 10/23/2020 Approved CHRIS CHRISTENSEN
Final 10/23/2020 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 10/23/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 10/23/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/23/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/23/2020 Approved CHRIS CHRISTENSEN