9791-9793 N ARLETA AVE 91331
Certificate Information: 9791-9793 N ARLETA AVE 91331
- Application / Permit
- 20014-20000-00835
- Plan Check / Job No.
- B20VN03223
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED CARPORT AND TWO STORY PORTION OF SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT (1600 SQ FT)
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 2/26/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Plan Check Approved | 3/16/2020 | JEROME MAGAT PALMA |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 7/31/2024 | MICHEL ABAJAN |
| CofO Issued | 8/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/27/2020 | ADRIAN CASTRO |
| ZA Case | Cleared | 3/16/2020 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C69781 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/31/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 3/31/2020 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/13/2020 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/16/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 4/16/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 4/16/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/16/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/27/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/27/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/27/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/27/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/7/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/7/2020 | Approved | MICHEL ABAJAN |
| Insulation | 5/7/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/7/2020 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 5/7/2020 | Partial Approval | MICHEL ABAJAN |
| Drywall Nailing | 5/26/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/26/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/22/2020 | Approved | MICHEL ABAJAN |
| Final | 7/22/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/22/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 7/22/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 7/22/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2020 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 7/22/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 4/3/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 4/5/2023 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 4/5/2023 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 4/5/2023 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 4/5/2023 | No Access for Inspection | MICHEL ABAJAN |
| Final | 7/31/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 7/31/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/31/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/31/2024 | Approved | MICHEL ABAJAN |