7716 N WISH AVE 91406
Certificate Information: 7716 N WISH AVE 91406
- Application / Permit
- 20014-20000-00828
- Plan Check / Job No.
- B20VN03207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT KITCHEN TO BEDROOM; ADD IRREGULAR SHAPES 20.2' X 14' AND 34.1' X 30' FOR NEW BATHROOM/BEDROOM EXPANSION AND NEW FAMILY ROOM/RELOCATED KITCHEN RESPECTIVELY. ALL WORKS ARE PER WFPP
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2020 | ALDOUS CHIC |
| Corrections Issued | 2/25/2020 | ALDOUS CHIC |
| Plan Check Approved | 2/26/2020 | ALDOUS CHIC |
| Issued | 2/26/2020 | LADBS |
| CofO in Progress | 7/9/2020 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2020 | DANIEL ORRANTE |
| CofO Issued | 7/9/2020 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2020 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 2/25/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/25/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/25/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/10/2020 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 3/10/2020 | Partial Inspection | JACK KARGODORIAN |
| Underground Mechanical | 3/16/2020 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 3/19/2020 | Approved | MATTHEW NELSON |
| Service/Power Release | 3/19/2020 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/24/2020 | Partial Approval | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 4/9/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/14/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/14/2020 | Approved | JENNIFER RABUCHIN |
| Gas Test | 4/14/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/14/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/14/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/14/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 4/17/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/17/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 4/17/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/20/2020 | Approved | JENNIFER RABUCHIN |
| Gas Test | 5/7/2020 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 5/7/2020 | Partial Inspection | MISAEL ESPARZA |
| Underground Mechanical | 5/7/2020 | Partial Inspection | MISAEL ESPARZA |
| Service/Power Release | 5/18/2020 | Not Ready for Inspection | TROY SANDERS |
| Final | 5/27/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/27/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2020 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 5/27/2020 | Approved | MISAEL ESPARZA |
| HVAC-Final | 6/10/2020 | Approved | JEFFREY PARD |
| Final | 6/12/2020 | OK to Issue CofO | JOHN HAYES |