1146 E 55TH ST 90011
Certificate Information: 1146 E 55TH ST 90011
- Application / Permit
- 20014-20000-00826
- Plan Check / Job No.
- B20VN03199
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" X 20'-0" DETACHED GARAGE AND ADD 15'-5" X 23'-0" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2020 | JENNIFER LEE |
| Corrections Issued | 3/2/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 4/23/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/2/2020 | RAPHAEL ROSAS |
| Issued | 8/5/2020 | APPLICANT |
| CofO in Progress | 5/13/2022 | JOAQUIN GREENOUGH |
| No Progress | 5/20/2022 | HORACE FULTZ |
| CofO in Progress | 5/20/2022 | JOAQUIN GREENOUGH |
| No Progress | 5/20/2022 | HORACE FULTZ |
| CofO in Progress | 5/20/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/12/2020 | CELINA MORENO |
| Sewer availability | Cleared | 5/12/2020 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 5/29/2020 | HELEN JADALI |
| ZI | Cleared | 5/29/2020 | HELEN JADALI |
| ZI | Cleared | 5/29/2020 | HELEN JADALI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 12/22/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 6/8/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 6/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/5/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/5/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/26/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 9/16/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 9/16/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 9/20/2021 | Approved | HORACE FULTZ |
| HVAC-Rough | 9/20/2021 | Approved | HORACE FULTZ |
| Wood Frame | 9/20/2021 | Approved | HORACE FULTZ |
| Insulation | 9/24/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 10/13/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/13/2021 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 11/5/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Shower Pan | 11/12/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/17/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | FREDDIE RIVERA |
| Final | 2/17/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/17/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 2/17/2022 | Approved | FREDDIE RIVERA |
| Final | 3/9/2022 | Corrections Issued | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Approved | HORACE FULTZ |
| Final | 4/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Sewer | 4/6/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 5/9/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/13/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |