5716 N TOBIAS AVE 91411
Certificate Information: 5716 N TOBIAS AVE 91411
- Application / Permit
- 20014-20000-00823
- Plan Check / Job No.
- B20VN03192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 27' 5" X 29' 5" TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/26/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/2/2020 | APPLICANT |
| Plan Check Approved | 5/28/2020 | GURUNATH NESARAJAH |
| Issued | 6/5/2020 | LADBS |
| CofO in Progress | 11/5/2020 | WILLIAM KUEHN |
| CofO Issued | 11/23/2020 | MICHAEL SMITH |
| Permit Finaled | 11/23/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 3/3/2020 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 4/28/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/26/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/9/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/11/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/15/2020 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/3/2020 | Approved | MATTHEW NUCKOLLS |
| HVAC-Rough | 7/3/2020 | Conditional Approval | MATTHEW NUCKOLLS |
| PLUMBING-Rough | 7/3/2020 | Approved | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 7/6/2020 | Approved | MISAEL ESPARZA |
| Green Building Rough | 7/6/2020 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 7/6/2020 | Approved | MISAEL ESPARZA |
| Insulation | 7/9/2020 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 7/9/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 7/14/2020 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/14/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 7/15/2020 | Approved | MISAEL ESPARZA |
| Sewer | 8/14/2020 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 8/14/2020 | Partial Approval | ARAM AVEDISIAN |
| Final | 9/14/2020 | Corrections Issued | WILLIAM KUEHN |
| Footing/Foundation/Slab | 9/14/2020 | Approved | WILLIAM KUEHN |
| Green Building Final | 9/14/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 9/14/2020 | Approved | WILLIAM KUEHN |
| Final | 10/5/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 10/27/2020 | Corrections Issued | DAVID MATSON |
| Final | 11/4/2020 | OK to Issue CofO | WILLIAM KUEHN |
| ELECTRICAL-Final | 11/13/2020 | Approved | WILLIAM KUEHN |