6718 N COSTELLO AVE 91405

Certificate Information: 6718 N COSTELLO AVE 91405

Application / Permit
20014-20000-00810
Plan Check / Job No.
B20VN03125
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert utility room to closet, remodel bathroom, add 13.75' x 13.92' new bedroom and 12' x 13.7' attached patio cover. All works are per design
Permit Issued
Issued on 4/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 2/24/2020 ALDOUS CHIC
Corrections Issued 2/24/2020 ALDOUS CHIC
Plan Check Approved 4/6/2020 RAPHAEL ROSAS
Issued 4/13/2020 LADBS
CofO in Progress 1/19/2021 MICHEL ABAJAN
Permit Finaled 2/13/2021 MICHAEL SMITH
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/24/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/28/2020 GUILLERMO PETRA
Sewer availability Cleared 2/28/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/20/2020 Conditional Approval WILLIAM KUEHN
Excavation/Setback/Form/Re-Bar 8/25/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Partial Inspection WILLIAM KUEHN
Green Building Rough 9/14/2020 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 10/20/2020 Approved MICHEL ABAJAN
HVAC-Rough 10/20/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 10/20/2020 Approved MICHEL ABAJAN
Wood Frame 10/23/2020 Corrections Issued MATTHEW NELSON
Wood Frame 10/30/2020 Approved JENNIFER RABUCHIN
Insulation 11/12/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 11/12/2020 Approved WILLIAM KUEHN
Shower Pan 11/12/2020 Approved WILLIAM KUEHN
Drywall Nailing 11/14/2020 Approved RAUL BARAJAS
Green Building Rough 11/14/2020 Approved RAUL BARAJAS
BUILDING-Rough-Frame 1/19/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/19/2021 Approved MICHEL ABAJAN
Final 1/19/2021 OK to Issue CofO MICHEL ABAJAN
Footing/Foundation/Slab 1/19/2021 Approved MICHEL ABAJAN
Green Building Final 1/19/2021 Approved MICHEL ABAJAN
HVAC-Final 1/19/2021 Approved MICHEL ABAJAN
PLUMBING-Final 1/19/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/19/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/19/2021 Approved MICHEL ABAJAN