20621 W PARTHENIA ST 91306

Certificate Information: 20621 W PARTHENIA ST 91306

Application / Permit
20014-20000-00801
Plan Check / Job No.
B20VN03078
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED IRR SHAPED (33'2-1/2" X 33'6-1/2") ACCESSORY DWELLING UNIT ADDN TO EX DETACHED GARAGE PER ENGR DESIGN
Permit Issued
Issued on 5/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/24/2020 HAYATO TSUCHIYA
Corrections Issued 2/26/2020 HAYATO TSUCHIYA
Building Plans Picked Up 2/26/2020 APPLICANT
Applicant returned to address corrections 4/28/2020 HAYATO TSUCHIYA
Plan Check Approved 5/8/2020 HAYATO TSUCHIYA
Issued 5/26/2020 LADBS
CofO in Progress 11/18/2020 DAVID STEPANYAN
Permit Finaled 11/18/2020 JOHN JANSON
CofO Issued 11/18/2020 JOHN JANSON
Permit Finaled 11/18/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/17/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/17/2020 LEE GUILBEAUX
Sewer availability Cleared 3/17/2020 LEE GUILBEAUX
Low Impact Development Cleared 4/20/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/22/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 6/12/2020 Partial Approval DAVID STEPANYAN
Underground Mechanical 6/12/2020 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 6/15/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 7/14/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 7/14/2020 Not Ready for Inspection DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 7/29/2020 Approved DAVID STEPANYAN
PLUMBING-Rough 7/29/2020 Corrections Issued DAVID STEPANYAN
HVAC-Rough 8/5/2020 Approved DAVID STEPANYAN
PLUMBING-Rough 8/5/2020 Approved DAVID STEPANYAN
Sewer 8/5/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 8/10/2020 Approved DAVID STEPANYAN
Green Building Rough 8/10/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 8/10/2020 Partial Approval DAVID STEPANYAN
Insulation 8/13/2020 Not Ready for Inspection DAVID STEPANYAN
Drywall Nailing 8/21/2020 Not Ready for Inspection DAVID STEPANYAN
Insulation 8/21/2020 Corrections Issued DAVID STEPANYAN
Drywall Nailing 8/27/2020 Approved DAVID STEPANYAN
Insulation 8/27/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/9/2020 Approved DAVID STEPANYAN
Shower Pan 9/9/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 11/2/2020 Corrections Issued DAVID STEPANYAN
Final 11/2/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 11/2/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 11/2/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 11/2/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Final 11/17/2020 Approved DAVID STEPANYAN
Final 11/17/2020 OK to Issue CofO DAVID STEPANYAN
Green Building Final 11/17/2020 Approved DAVID STEPANYAN
HVAC-Final 11/17/2020 Approved DAVID STEPANYAN
PLUMBING-Final 11/17/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 11/17/2020 Approved DAVID STEPANYAN