20621 W PARTHENIA ST 91306
Certificate Information: 20621 W PARTHENIA ST 91306
- Application / Permit
- 20014-20000-00801
- Plan Check / Job No.
- B20VN03078
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED IRR SHAPED (33'2-1/2" X 33'6-1/2") ACCESSORY DWELLING UNIT ADDN TO EX DETACHED GARAGE PER ENGR DESIGN
- Permit Issued
- Issued on 5/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 2/26/2020 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 2/26/2020 | APPLICANT |
| Applicant returned to address corrections | 4/28/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/8/2020 | HAYATO TSUCHIYA |
| Issued | 5/26/2020 | LADBS |
| CofO in Progress | 11/18/2020 | DAVID STEPANYAN |
| Permit Finaled | 11/18/2020 | JOHN JANSON |
| CofO Issued | 11/18/2020 | JOHN JANSON |
| Permit Finaled | 11/18/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/17/2020 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 4/20/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/22/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Durand,, Paul Henri; Lic. No.: S4222 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 6/12/2020 | Partial Approval | DAVID STEPANYAN |
| Underground Mechanical | 6/12/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 6/15/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 7/14/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 7/14/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 7/29/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 7/29/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 8/5/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 8/5/2020 | Approved | DAVID STEPANYAN |
| Sewer | 8/5/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 8/10/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 8/10/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 8/10/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 8/13/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Drywall Nailing | 8/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Insulation | 8/21/2020 | Corrections Issued | DAVID STEPANYAN |
| Drywall Nailing | 8/27/2020 | Approved | DAVID STEPANYAN |
| Insulation | 8/27/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 9/9/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 9/9/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/2/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 11/2/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 11/2/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Final | 11/2/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 11/2/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/17/2020 | Approved | DAVID STEPANYAN |
| Final | 11/17/2020 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 11/17/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 11/17/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 11/17/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 11/17/2020 | Approved | DAVID STEPANYAN |