13723 W BRACKEN ST 91331

Certificate Information: 13723 W BRACKEN ST 91331

Application / Permit
20014-20000-00786
Plan Check / Job No.
B20VN03010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
14'-11" X 33'-10" IRREG SHAPED ADDITION (381 SF) TO AND CONVERT (E) DETACHED GARAGE (323 SF) TO ACCESSORY DWELLING UNIT (704 SF IN TOTAL). CONSTRUCTION PER WFPP.
Permit Issued
Issued on 8/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 2/25/2020 JEROME MAGAT PALMA
Corrections Issued 2/25/2020 JEROME MAGAT PALMA
Plan Check Approved 7/23/2020 CHUNG-WEN CHUANG
Building Plans Picked Up 7/24/2020 APPLICANT
Issued 8/5/2020 APPLICANT
CofO in Progress 3/19/2021 GREGG CUMMINGS
Permit Finaled 6/26/2021 MICHAEL SMITH
CofO Issued 6/26/2021 MICHAEL SMITH
Permit Finaled 6/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/2/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/2/2020 GABRIEL ROBLES
Sewer availability Cleared 3/2/2020 GABRIEL ROBLES
Low Impact Development Cleared 7/8/2020 ANDRES COVARRUBIAS
Construction near power lines Cleared 7/9/2020 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 7/14/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor D H Property Maintenance Inc; Lic. No.: 985811-B 11312 COVELLO STREET      SUN VALLEY, CA 91352

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/13/2020 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 8/17/2020 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 8/26/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 9/8/2020 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/8/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 9/8/2020 Not Ready for Inspection GREGG CUMMINGS
Underground Mechanical 9/8/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 9/16/2020 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 9/16/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 9/16/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 9/23/2020 Approved GREGG CUMMINGS
Green Building Rough 9/23/2020 Approved GREGG CUMMINGS
HVAC-Rough 9/23/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 9/23/2020 Approved GREGG CUMMINGS
Insulation 9/29/2020 Approved GREGG CUMMINGS
Drywall Nailing 10/2/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/2/2020 Approved GREGG CUMMINGS
Final 2/9/2021 Corrections Issued GREGG CUMMINGS
Gas Test 2/9/2021 Approved GREGG CUMMINGS
Green Building Final 2/9/2021 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/9/2021 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 2/9/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 3/19/2021 Approved GREGG CUMMINGS
Final 3/19/2021 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 3/19/2021 Approved GREGG CUMMINGS
PLUMBING-Final 3/19/2021 Approved GREGG CUMMINGS