13766 W HUBBARD ST 91342
Certificate Information: 13766 W HUBBARD ST 91342
- Application / Permit
- 20014-20000-00781
- Plan Check / Job No.
- B20VN02998
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ATTACHED REC-ROOM TO THE REAR OF (E) SFD.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | YAQUB MIRZA |
| Plan Check Approved | 2/20/2020 | YAQUB MIRZA |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 7/24/2020 | MISAEL ESPARZA |
| Permit Finaled | 8/8/2020 | MICHAEL SMITH |
| CofO Issued | 8/8/2020 | MICHAEL SMITH |
| Permit Finaled | 8/8/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/26/2020 | Corrections Issued | TROY SANDERS |
| Special/Order Compliance | 2/26/2020 | Approved | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 3/4/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 3/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 3/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/10/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/10/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/10/2020 | Partial Inspection | MATTHEW NELSON |
| Green Building Rough | 4/10/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 4/10/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/10/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/10/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 4/15/2020 | Approved | TROY SANDERS |
| Final | 6/16/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Final | 6/16/2020 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/16/2020 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 6/16/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/23/2020 | Approved | MISAEL ESPARZA |
| Final | 7/23/2020 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 7/23/2020 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 7/23/2020 | Approved | MISAEL ESPARZA |