16850 W HALSEY ST 91344
Certificate Information: 16850 W HALSEY ST 91344
- Application / Permit
- 20014-20000-00777
- Plan Check / Job No.
- B20VN02978
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 21' X 2' 6" TO (E) ATTACHED GARAGE, CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADD 12' X 12' IRR.-SHAPE MEZZANINE STORAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 6/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/25/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Plan Check Approved | 3/6/2020 | GURUNATH NESARAJAH |
| Issued | 3/9/2020 | LADBS |
| CofO in Progress | 3/14/2022 | MICHAEL TEMPLE |
| CofO Issued-Status Void | 6/8/2022 | MICHAEL SMITH |
| Permit Finaled-Status Void | 6/8/2022 | MICHAEL SMITH |
| Re-Activate Permit | 6/13/2022 | MICHAEL SMITH |
| CofO Corrected | 6/13/2022 | MICHAEL SMITH |
| Permit Finaled | 6/13/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 3/2/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2020 | Not Ready for Inspection | MARK JOHNSON |
| Deputy Drilled-In Anchors | 4/1/2020 | Partial Approval | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 5/27/2020 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 5/29/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 5/29/2020 | Approved | MARK JOHNSON |
| Insulation | 6/2/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 6/5/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/12/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 6/12/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 6/18/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 7/10/2020 | Approved | MARK JOHNSON |
| Final | 9/23/2020 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 9/23/2020 | Approved | MARK JOHNSON |
| Green Building Final | 9/23/2020 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 9/23/2020 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 9/23/2020 | Approved | MARK JOHNSON |
| Final | 2/9/2021 | Corrections Issued | MARK JOHNSON |
| Final | 3/11/2022 | OK to Issue CofO | MICHAEL TEMPLE |