2444 N SILVER LAKE BLVD 90039

Certificate Information: 2444 N SILVER LAKE BLVD 90039

Application / Permit
20014-20000-00772
Plan Check / Job No.
B20VN02939
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A NEW IRREGULAR 11'x11'4" BATHROOM, INTERIOR ALTERATION TO REVISE BEDROOM ENTRANCE, AND EXTERIOR ALTERATION TO REPLACE WINDOWS AND ADD A NEW SKYLIGHT.ALL WORK DONE PER WFPP.
Permit Issued
Issued on 11/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 LUIS RINCON
Corrections Issued 2/20/2020 LUIS RINCON
Plan Check Approved 6/2/2020 ARTIN ZARUKIAN
Issued 11/6/2020 APPLICANT
CofO in Progress 5/13/2022 THOMAS LOGRASSO
Permit Finaled 7/29/2022 DEROLD HAUFF
CofO Issued 7/29/2022 DEROLD HAUFF
Permit Finaled 7/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/4/2020 JAMES KHO
Roof/Waste drainage to street Cleared 5/4/2020 JAMES KHO
Grading Pre-Inspection Cleared 5/31/2020 LUIS RINCON

Contact Information

Contractor Pavlovich Construction Co; Lic. No.: 388868-B 22817 VENTURA BLVD #1001      WOODLAND HILLS, CA 91364

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/3/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/3/2020 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 3/9/2021 Partial Inspection RUBEN SALAS
Footing/Foundation/Slab 3/9/2021 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 4/1/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/12/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 5/6/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/6/2021 Corrections Issued HAMIK HARTOUNIAN
Insulation 5/14/2021 Partial Approval ROBERT VORHIS
PLUMBING-Rough 5/14/2021 Partial Approval ROBERT VORHIS
Drywall Nailing 5/26/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Approved ROBERT VORHIS
Wood Frame 5/26/2021 Not Ready for Inspection ROBERT VORHIS
ELECTRICAL-Rough 6/17/2021 Approved CRAIG VAUGHAN
HVAC-Rough 6/17/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/17/2021 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/17/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/23/2021 Approved RICHARD STEINBACH
ELECTRICAL-Rough 6/23/2021 Approved RICHARD STEINBACH
Green Building Rough 6/23/2021 Approved RICHARD STEINBACH
PLUMBING-Rough 6/23/2021 Approved RICHARD STEINBACH
Insulation 6/29/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/29/2021 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/29/2021 Approved THOMAS LOGRASSO
Final 10/21/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 10/21/2021 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/21/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 10/21/2021 Approved THOMAS LOGRASSO
Final 2/16/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 2/16/2022 Approved THOMAS LOGRASSO
Final 5/12/2022 OK to Issue CofO THOMAS LOGRASSO