11614 W TERRYHILL PL 90049
Certificate Information: 11614 W TERRYHILL PL 90049
- Application / Permit
- 20014-20000-00766
- Plan Check / Job No.
- B20VN02893
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (22'-6" X 27') IRREGULAR SHAPED 1-STORY ADDITION AND MAJOR REMODEL TO (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofO Issued on 6/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Green Plans Picked Up | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | RAPHAEL ROSAS |
| Corrections Issued | 3/16/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 3/16/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/18/2020 | APPLICANT |
| Plan Check Approved | 6/3/2020 | RAPHAEL ROSAS |
| Issued | 6/3/2020 | APPLICANT |
| CofO in Progress | 6/14/2022 | MICHAEL PELHAM |
| Permit Finaled | 6/16/2022 | DANIEL ORRANTE |
| CofO Issued | 6/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 4/21/2020 | MICHAEL AYERS |
| Sewer availability | Cleared | 4/21/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 5/21/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/28/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/3/2020 | RAPHAEL ROSAS |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Parker Bldg & Concrete; Lic. No.: 744777-B | 1075 ELMHURST DR CORONA, CA 92880 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2020 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/6/2020 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/6/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Barrier | 7/6/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Subgrade | 7/6/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/23/2020 | Approved | CARLOS MATAMOROS |
| METHANE-Barrier | 7/23/2020 | Approved | CARLOS MATAMOROS |
| METHANE-Subgrade | 7/23/2020 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 9/18/2020 | Conditional Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/7/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 10/7/2020 | Corrections Issued | CARLOS MATAMOROS |
| METHANE-Rough | 10/7/2020 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/7/2020 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/21/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 10/21/2020 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/21/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/29/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/29/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 10/29/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 10/29/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 10/29/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 10/29/2020 | Approved | CARLOS MATAMOROS |
| METHANE-Rough | 10/29/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 11/6/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/6/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 11/16/2020 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 4/22/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 4/23/2021 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 4/23/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 4/23/2021 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 1/10/2022 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Grading Pre-Inspection | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Final | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Service/Power Release | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 1/10/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 3/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 3/22/2022 | Approved | CARLOS MATAMOROS |
| Green Building Final | 3/22/2022 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 3/22/2022 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/22/2022 | Corrections Issued | CARLOS MATAMOROS |
| Final | 3/30/2022 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 3/30/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/13/2022 | Approved | CARLOS MATAMOROS |
| Final | 6/13/2022 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Final | 6/13/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 6/13/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Approved | CARLOS MATAMOROS |